Choose Solar & storage for your property
From electricity needs to a preliminary system and budget. No contact details required.
Automatic pre-survey calculations
Enter your sizing input to see module area, access area, roof requirement, module mass, capacity and electrical configuration.
Developed and operated by QuangAnhcons. Preliminary results require site survey and written confirmation before ordering or construction.
Solar 8.21.0 · QAC-UI-QUOTE 1.1.1
© 2026 QUANG ANH CONSTRUCTION ELECTRICITY COMPANY LIMITED. Quotation prepared by QuangAnhcons. Please retain the issuer name and reference when saving or sharing. Third-party names and materials belong to their respective owners.
Executive answer: a rooftop-solar investment model is only as credible as the assumptions that connect the roof, the factory load, the electrical interface and the commercial contract. A finance team should not accept one headline payback period. It should require an auditable chain from measured load and solar resource through hourly energy flows, losses, availability, degradation, operating cost, contract terms and downside cases.
This guide is for an overseas investor reviewing a Vietnam factory proposal. It does not quote a market price, promise a yield, interpret tax law or declare a project compliant. The worked figures are deliberately hypothetical and must be replaced by project evidence.
1. Start with the decision, not the spreadsheet
Ask what the model is meant to decide: proceed to detailed feasibility, compare EPC bids, choose a self-funded or third-party structure, approve a capital budget, or verify a performance guarantee. Each decision needs different confidence. A preliminary map-based estimate can screen a site; it should not be treated as a bankable energy forecast.
The finance pack should identify the model owner, base date, currency, tax basis, financing boundary, calculation period, escalation basis and version. It should also state who approves technical inputs. Otherwise an apparently precise internal rate of return can hide unresolved engineering choices.
2. Separate evidence, assumptions and outputs
| Class | Examples | Owner challenge |
|---|---|---|
| Measured evidence | Interval load data, utility bills, roof survey, structural report, outage log | Period, completeness, meter boundary and abnormal months |
| Design input | DC capacity, inverter capacity, orientation, cable route, transformer point | Revision, constraint and responsible designer |
| Forecast assumption | Solar resource, soiling, clipping, availability, degradation | Source, uncertainty, correlation and whether already embedded |
| Commercial input | Avoided-energy value, export value, O&M, insurance, replacement, financing | Contract evidence, indexation, currency and excluded cost |
| Model output | Self-consumed energy, cash flow, NPV, IRR, payback | Sensitivity, reconciliation and decision threshold |
Do not let an output become an assumption in the next revision without its lineage. A quoted “specific yield” may already include temperature, wiring, inverter and availability losses. Deducting those losses again understates production; adding a separate availability uplift overstates it.
3. Challenge the solar resource and time basis
The World Bank’s Global Solar Atlas is useful for preliminary resource screening and consistent geographic comparison. It is not a substitute for a project-specific assessment of the roof plane, shading, horizon, weather variability and system configuration. Record the dataset version, coordinates, plane-of-array method and period represented.
An annual irradiation number alone cannot calculate factory self-consumption. The model needs a time series at an interval suitable for the decision—hourly at minimum for a first commercial assessment, and often 15 or 30 minutes where demand peaks, export limits or shift changes matter. Solar and load profiles must use the same time zone and daylight-saving convention. Vietnam does not use daylight saving, but imported corporate datasets may have been normalized to another zone.
Check whether leap days, missing intervals and meter resets were handled. Show annual totals before and after cleaning. If a new production line is planned, keep the measured historical load and the future adjustment as separate scenarios.
4. Rebuild the year-one energy bridge
A transparent energy bridge starts with nameplate capacity and specific yield:
E_PV,1 = P_DC × Y_specific
For a hypothetical 2.4 MWp array and a simulated year-one specific yield of 1,420 kWh/kWp, the result is:
2,400 kWp × 1,420 kWh/kWp = 3,408,000 kWh = 3,408 MWh
This is not a Vietnam benchmark or guarantee. It is a unit check. The proposal must state which losses the 1,420 kWh/kWp already contains.
Then split energy at the agreed meter boundary:
E_PV = E_self-consumed + E_exported + E_curtailed
If the same hypothetical case has 92% self-consumption and no separate curtailment because curtailment is already embedded in the simulation, then:
- Self-consumed energy = 3,408 MWh × 92% = 3,135.36 MWh.
- Exported energy = 3,408 MWh × 8% = 272.64 MWh.
- Reconciliation = 3,135.36 + 272.64 = 3,408 MWh.
The model must not assign the same unit value to both streams unless contracts actually support it. If export is prohibited or uncompensated, exported energy may have no modeled revenue and should trigger a sizing or controls review.
5. Test self-consumption instead of assuming it
Self-consumption depends on coincidence, not annual consumption. A factory using 12,000 MWh per year can still export at noon if weekend and holiday demand is low. Conversely, a smaller factory with continuous process loads may absorb more solar.
Request these plots:
- Monthly factory load, PV generation, self-consumption, export and curtailment.
- Representative weekday, weekend and shutdown-day profiles.
- Duration curves for import, export and PV output.
- Metered demand before and after PV at the tariff demand interval.
- Energy balance at the utility meter, PV meter and major internal meters.
Confirm whether auxiliary loads, transformer losses and inverter station consumption sit inside or outside the benefit boundary. The factory electrical metering-boundary guide explains why meter ownership and reconciliation must be fixed before performance reporting.
6. Do not double-count demand-charge savings
Rooftop solar can reduce daytime demand, but it does not automatically reduce the billing maximum. The peak may occur after sunset, during a cloud transient, at production start-up or when the PV system is unavailable. A model claiming demand savings should reproduce the tariff demand interval and apply PV output to the same interval load series.
Keep three outputs separate:
- Imported energy avoided, in kWh.
- Maximum or contracted demand change, in kW or kVA under the actual tariff method.
- Production-resilience value, which rooftop PV without islanding and an appropriately designed energy source may not provide during a grid outage.
Do not assign outage-avoidance value to a normal grid-following PV system merely because panels are present. Backup operation requires an approved electrical architecture, controls, protection, operating philosophy and often storage or another grid-forming source.
7. Make every loss explicit and non-overlapping
| Loss or constraint | Evidence to request | Common modeling error |
|---|---|---|
| Shading | 3D model, horizon and obstruction assumptions | Using a generic percentage despite rooftop equipment |
| Temperature | Module coefficient, weather series and mounting method | Using standard-test-condition power as operating output |
| Soiling | Site conditions, cleaning strategy and sensitivity | Claiming a fixed loss without access or water constraints |
| Mismatch and DC wiring | String design, cable calculation and model settings | Deducting the same loss in software and spreadsheet |
| Inverter efficiency/clipping | Efficiency curve, DC/AC ratio and time-step simulation | Treating nameplate efficiency as constant |
| AC wiring/transformer | Route, conductor, loading and transformer boundary | Ignoring losses outside the inverter output |
| Availability | Definition, exclusions, response times and data source | Using a percentage without defining denominator |
| Export/curtailment | Connection condition and controls logic | Calling curtailed energy “self-consumed” |
Ask for a loss diagram that reconciles simulated irradiance to net AC energy at the financial meter. If two bidders use different meter boundaries, normalize them before comparing price or yield.
8. Treat availability as a contract definition
Availability may be time-based, energy-weighted, inverter-based or plant-level. Exclusions for utility outage, owner shutdown, force majeure, communications failure and planned maintenance can materially change the number. A high availability percentage can coexist with lost energy if outages occur during high irradiance.
IEC 61724-1:2021 provides terminology and methods for PV performance monitoring, including monitoring-system classes and data-quality concepts. IEC TS 61724-2:2025 defines a power performance index test for grid-connected PV systems under unconstrained test conditions. These scopes help the owner define measurable evidence; they do not create a project guarantee by themselves.
Require the proposal to state:
- Availability formula, measurement point and time resolution.
- Excluded events and approval process.
- Data substitution rules for failed sensors or communications.
- Response and restoration obligations.
- How availability, performance ratio and energy guarantee interact.
9. Audit degradation without turning it into a slogan
Performance loss is not one universal module number. IEA PVPS research shows that methods, data quality and missing data affect calculated performance-loss rates. The model should identify whether degradation applies to DC module power, system energy or a contractual guaranteed profile.
For illustration, if year-one net energy is 3,408 MWh and a hypothetical annual performance loss rate is 0.45%, year 10 before other scenario changes is:
E_10 = 3,408 × (1 − 0.0045)^9 ≈ 3,272 MWh
The exponent is nine because year one is the reference. Do not apply ten degradation steps to year 10. More importantly, do not use this illustrative rate as a promise. Require technology-, climate-, warranty- and dataset-specific evidence, plus downside sensitivity.
IEC 61215-1:2021 addresses design qualification of terrestrial PV modules, but its public scope expressly notes that qualification test results are not a quantitative prediction of module lifetime. IEC 61730-1:2023 addresses module construction requirements for electrical and mechanical safety. A certificate reference should therefore be matched to the exact module family and does not replace project reliability analysis.
10. Build a finance model that can be audited
The operating cash-flow structure should be visible:
Net operating benefit_t = avoided import value_t + export value_t + verified incentives_t − O&M_t − insurance_t − lease/fee_t − replacement_t − other project costs_t
Then discount project cash flows consistently:
NPV = Σ CF_t / (1 + r)^t
State whether the discount rate is nominal or real and keep inflation treatment consistent. Separate project economics from financing cash flows unless the decision specifically requires equity returns. List taxes, depreciation, withholding, foreign-exchange and accounting treatment as inputs requiring qualified review; do not infer them from an EPC proposal.
Simple payback ignores the timing of cash flows after recovery and should not be the only decision metric. Show at least NPV, IRR where mathematically meaningful, discounted payback and cumulative cash flow, with model checks that flag multiple sign changes or non-convergent IRR.
11. Define avoided cost from the bill, not a headline tariff
The value of one self-consumed kWh is not automatically the total bill divided by total kWh. Separate energy charges, demand charges, fixed charges, taxes and pass-through items. Determine which components actually change when grid import falls. Use bills covering a representative period and document contract changes expected during the model horizon.
If prices are modeled to escalate, show the base source, start date, escalation formula and cap or downside. A foreign investor should also test currency mismatch: revenue or savings may be in VND while modules, inverters, debt service or group reporting may be linked to another currency.
12. Include all life-cycle costs and residual obligations
- Engineering, permits and owner’s engineer.
- Structural reinforcement and roof remediation.
- MV/LV interface changes, switchgear, protection, metering and communications.
- Shutdowns, temporary works and production coordination.
- O&M labour, cleaning, monitoring, testing and vegetation/drainage where relevant.
- Inverter or component replacement assumptions.
- Insurance, security, spare parts and software/service subscriptions.
- Roof access, dismantling/reinstatement and end-of-term removal.
- Waste management and asset disposal obligations.
Do not hide a necessary roof replacement outside the investment case. Conversely, do not charge the solar project for unrelated roof work without identifying the allocation rule.
13. Challenge structural and electrical constraints before approving yield
A finance model should carry gates for roof capacity, waterproofing responsibility, fire access, drainage, lightning protection, earthing, cable routes, inverter locations, transformer loading, protection coordination, power quality and the connection agreement. The rooftop-solar feasibility data guide lists the technical inputs needed before an owner relies on a yield estimate.
TCVN 7447-7-712:2019, equivalent to IEC 60364-7-712:2017, covers low-voltage electrical installations for solar PV supply systems. The project team must confirm the applicable standard set, Vietnamese regulations, utility or industrial-park requirements and contract editions at the design date. A reference in the model is not proof of compliance.
14. Model production disruption and HSE as decision risks
Rooftop work can affect live production through crane movements, roof access, dropped-object risk, water ingress, hot work, electrical tie-ins and planned outages. The investment pack should include a construction sequence, shutdown assumptions and responsibility for production coordination.
Minimum HSE planning should address fall prevention, rescue, lifting, roof fragility, weather, fire, DC hazards, lockout/tagout, test-for-dead, energized-work prohibition or controlled exception, and emergency access. Only competent personnel using approved procedures should perform isolation, testing and commissioning. A low-price model that omits safe access and shutdown cost is not comparable with a complete scope.
15. Tie the assumptions to FAT, SAT and acceptance evidence
| Stage | Owner evidence | Financial assumption protected |
|---|---|---|
| Design review | Energy model, loss bridge, load match, SLD, protection and meter boundary | Yield and self-consumption |
| Procurement | Approved module/inverter data, qualification references, warranty terms | Efficiency, degradation and replacement |
| FAT/document review | Inverter/switchgear tests, settings, communications and certificates | Availability and interface readiness |
| Installation ITP | Structure, torque, cable, earthing, insulation and labeling records | Reliability and safety |
| SAT/commissioning | Functional, protection, meter, monitoring and export-control tests | Commercial operation date and measurable output |
| Performance test | Approved method, weather/data filters and uncertainty treatment | Guarantee acceptance |
| Handover | As-builts, settings, spares, training, O&M and baseline records | Operating cost and future auditability |
The acceptance plan should state what happens when data are unavailable or the test window is constrained. Do not let a short commissioning snapshot become an unqualified 20-year yield promise.
16. Require base, downside and break-even cases
A robust investment committee pack should show more than one deterministic case.
| Variable | Base-case evidence | Downside challenge | Break-even question |
|---|---|---|---|
| Specific yield | Versioned simulation and site inputs | Lower resource or higher losses | What yield makes NPV zero? |
| Self-consumption | Interval load match | Weekend, shutdown or line relocation | Minimum absorbed share? |
| Availability | Contract definition and service plan | Long spare-part lead time | Maximum lost-energy days? |
| Degradation | Technology and warranty basis | Higher performance loss | Maximum annual rate? |
| Avoided cost | Bill component analysis | Lower variable charge | Minimum unit value? |
| Capital cost | Comparable scope and exclusions | Roof/MV variation | Maximum total installed cost? |
| Schedule | Permits, procurement and outage plan | Delayed commercial operation | Latest acceptable COD? |
Run variables individually and in a coherent downside case. Solar resource, clipping, export and self-consumption can be correlated; combining independent “best cases” produces an unrealistic result.
17. Compare commercial structures on the same boundary
Self-funded EPC, equipment lease, rooftop lease, energy-service agreement and third-party power structures allocate ownership, operating responsibility and risk differently. Normalize them on:
- Energy and meter boundary.
- Contract term and termination rights.
- Roof access and reinstatement.
- Performance and availability definitions.
- Tariff/indexation and currency.
- Change in factory load or site closure.
- Insurance, damage, step-in and lender rights.
- Asset transfer or removal at term end.
Do not compare an EPC capex number with a service price as if they are equivalent cash flows. For a third-party proposal, legal, tax and electricity-market treatment require project-specific professional review.
18. RFQ return schedule for a finance-grade proposal
Ask bidders to return a structured assumption register with:
- Hourly energy model and readable annual summary.
- Weather/resource source, coordinates, period and uncertainty.
- Factory load dataset, cleaning log and future-load scenarios.
- Loss diagram with meter boundary and non-overlap check.
- Self-consumption, export and curtailment calculation.
- Availability, degradation and performance-test definitions.
- CAPEX/BOQ inclusions, exclusions, taxes and currency.
- O&M, replacement, spare and end-of-term assumptions.
- Programme, permits, shutdowns and owner dependencies.
- Base, downside, upside and break-even outputs.
- Model file with formulas accessible for audit.
For scope benchmarking, the industrial rooftop-solar service page describes QuangAnhcons’ owner-side electrical and construction interfaces. BESS should be evaluated separately; see the industrial BESS owner-requirements brief before assigning storage value to a solar case.
19. FAQ
Can the Global Solar Atlas be used for investment approval?
It is valuable for preliminary screening. Investment approval should document project-specific roof, shading, weather, design, loss and uncertainty inputs at the confidence appropriate to the decision.
Is a higher DC/AC ratio always better?
No. It may improve inverter utilization but can increase clipping and thermal or interface constraints. Evaluate hourly energy and commercial value, not only installed DC capacity.
Does module qualification prove a 25-year output?
No. IEC 61215 design qualification is not a quantitative lifetime prediction. Review exact product evidence, warranty terms, degradation assumptions, environment and operating strategy.
Should export energy be valued?
Only under a verified contractual and regulatory basis. If export is constrained or uncompensated, model it accordingly and consider sizing or controls changes.
Can rooftop solar provide backup during a grid outage?
Not by assumption. The architecture must be designed and approved for islanded or backup operation with appropriate sources, controls, protection and operating procedures.
What is the most important audit file?
The assumption register linking each model input to its source, owner, date, uncertainty and approval. It lets the finance team understand what changed and why.
Owner action checklist
- Freeze the decision purpose, model boundary and base date.
- Reconcile interval load, simulated PV, self-consumption, export and curtailment.
- Eliminate duplicated losses and unsupported demand savings.
- Define availability, degradation and performance tests contractually.
- Include roof, electrical interface, HSE, outages, O&M and end-of-term costs.
- Review base, downside and break-even cases.
- Require formulas and evidence—not only a PDF summary.
QuangAnhcons can help an FDI owner structure the technical assumption register, electrical interface, BOQ boundary, ITP and commissioning evidence for a factory rooftop-solar evaluation in Vietnam. The starting package should include 12 months or more of interval load data, bills, roof drawings, structural information, the proposed single-line diagram and the commercial term sheet. Final legal, tax, financing and acceptance decisions remain with the owner’s authorized advisers and project representatives.
[contact-form-7 id="7239967" title="Contact form 1"]Substation budget estimate
Select the capacity, route lengths and package to view your indicative budget and electrical parameters.
Request a project quotation
Send your project details, BOQ or drawings to request a formal quotation. Fields marked * are required.
Quotation scope
Applies to one EVN-supplied substation with oil-immersed transformers at 22/0.4 kV (single-phase: 12.7/0.23 kV), with MV metering VTs/CTs supplied by EVN. The estimate includes the selected equipment, installation, earthing, transformer-to-main-breaker connections, design and connection documentation, and coordination of testing and utility acceptance.
Kiosk, integrated steel-pole and indoor substations include MV switchgear and the entered underground cable route. Other outdoor arrangements use the relevant protection configuration. The final diagram must meet the project connection requirements.
Excludes VAT, cables from the substation switchboard to the MSB/loads, live-line work, harmonic reactors, weak-ground treatment or special piling, land and special fire-protection provisions. Underground routes assume normal construction conditions and exclude road drilling and special reinstatement.
Prices are indicative investment budgets. A formal quotation follows site assessment and agreement on the configuration. Electrical selections are preliminary and require design verification before installation.
Capacity range and application conditions
The catalogue defines the enquiry range of this tool, not universal TCVN capacity limits. Single pole-mounted transformers: 15–100 kVA; three-unit banks: 3×15–3×100 kVA. Platform substations: 100–630 kVA. Steel-pole substations: 100–630 kVA; 750/800 kVA require design verification and local approval. Ground-mounted, kiosk and indoor configurations: 50–10,000 kVA. Not every configuration has a package price or the same structural design.
Reference: EVN Decision 1299/QD-EVN dated 3 November 2017, Volume 1, sections 3.3–3.4. Check the current requirements of the responsible utility before implementation. Kiosks must meet manufacturer ratings and testing requirements (IEC 62271-202); indoor and ground-mounted arrangements must meet project layout, ventilation, structural and fire-protection requirements. For multiple transformers, specify the quantity and capacity of each unit.
Developed by QuangAnhcons · © 2026 QuangAnhcons. Code licensed under GPL-2.0-or-later. Standards and manufacturer data belong to their respective owners.


Related Posts
Rooftop Solar Investment Assumptions: A Finance-Team Challenge List for Vietnam Factories
Audit rooftop-solar investment assumptions for a Vietnam factory: load matching, yield, losses, availability, degradation, cash-flow [...]
Material Traceability for Factory Electrical Packages: Records an FDI Owner Can Audit
Define auditable material traceability for factory electrical packages: serial and batch links, receipt and quarantine, [...]
Electrical EPC Training Deliverables: An Owner’s Contract Guide
Define electrical EPC training by role, task, revision, safety boundary and acceptance evidence. Includes an [...]
Electrical Single Points of Failure: Rank the Production Consequence
Build a factory electrical consequence register around functions, shared dependencies and credible recovery paths. Compare [...]
Shared BESS for Factory Tenants: Separate Control from Energy Allocation
Define shared BESS electrical, command and tenant allocation boundaries before procurement, with a checked common-meter [...]
Electrical Handover Dossier: Make It Usable for an Overseas Facility Team
Specify an electrical handover dossier that an overseas facility team can actually use: asset links, [...]
Switchboard FAT Report Review: Evidence Before Dispatch
Review the switchboard FAT evidence chain before dispatch: assembly identity, drawing revisions, verification records, actual [...]
Factory Substation Delivery: Prove the Access Route Before Dispatch
Build a route evidence pack before dispatching factory electrical equipment: shipping envelopes, access constraints, receiving [...]
Owner-Supplied Electrical Equipment: Custody and Acceptance for a Vietnam Factory
Agree receipt, custody, preservation, technical release and operational acceptance when a factory owner buys electrical [...]
Factory Electrical Metering Boundaries: An Energy Reporting Brief
Define factory electrical metering boundaries before comparing energy performance: separate grid exchange, generation, battery flows, [...]
Oct
Electrical Maintenance Tender Scope for an FDI Factory: Assets, Access and Evidence
Prepare a comparable electrical maintenance tender for an FDI factory: asset scope, outage interfaces, workload [...]
Oct
Industrial BESS Owner Requirements in Vietnam: A Procurement Brief Bidders Can Price
Define an industrial BESS owner requirement for a Vietnam factory: AC boundary, duty, safety, interfaces, [...]
Oct
Electrical Operational Readiness for a New Vietnam Factory: Owner Checklist
Use an owner-side electrical operational readiness checklist for a new Vietnam factory: configuration, protection, machine [...]
Oct
Electrical Inspection and Test Plans: An Owner Guide for FDI Factories
Build an owner-level electrical ITP for a Vietnam factory: acceptance baselines, witness and hold points, [...]
Oct
Factory electrical interface register: close MV/LV and OEM boundaries before procurement
A project-ready electrical interface register connects the utility, transformer, MSB, OEM machines, civil works and [...]
Oct
Harmonics in Transmission and Distribution Power Systems: From 500 kV to End-Use Loads
A rigorous power-quality monograph from 500 kV transmission to end-use equipment, covering Fourier spectra, symmetrical [...]
BESS end-of-warranty acceptance: contract for net AC-deliverable energy
Define BESS end-of-warranty capacity at a named AC meter, not an ambiguous DC nameplate; includes [...]
Oct
Size an industrial standby generator from essential-load steps, not transformer kVA
A factory standby-generator procurement guide with a worked six-group P/Q load example, transfer sequence, motor-start [...]
Oct
Before choosing breaker kA ratings: build a complete factory fault-case register
An electrical fault-case register separates maximum breaking duty from minimum-fault protection sensitivity, with documented grid, [...]
Oct
Imported production lines: turn motor ratings into an auditable factory P/Q load schedule
A worked industrial load schedule converts imported machine shaft kW to active and reactive demand, [...]
Oct