An FDI factory electrical project can have sound individual technical drawings and still fail at the points between contracts. The imported production machine has a defined incoming supply; the Vietnamese electrical contractor has a feeder drawing; the civil contractor has a foundation; and the utility or industrial-park distributor has a connection agreement. The design can fall apart when no document identifies who owns the last five metres of cable, the gland plate, neutral arrangement, control interlock, trench opening or final energization record.
A useful electrical interface register is not a directory of subcontractors. It is a controlled decision log connecting a physical boundary to the correct design revision, an accountable producer, an acceptance criterion and a delivery milestone. This guide explains how to build that register across MV, LV and process equipment, with a worked hypothetical example, sample hold points and an RFQ structure for industrial owners and EPC procurement teams in Vietnam.
Prepared for QuangAnhcons · Editorial focus: cross-package electrical delivery for factories · Sources checked: 10 October 2026. The example roles, sizes and dates are illustrative discussion tools and not a real project contract.
Why a package boundary needs an equipment point, not a vague phrase
Statements such as “EPC to provide complete power” or “machine supplier to connect all equipment” leave too much open. An engineer needs a physical point or document deliverable that can be inspected. The upstream endpoint could be the transformer LV bushings, MSB outgoing terminals, an MDB incoming ACB or the machine control cabinet incomer. At every boundary, specify whether the responsibility includes supply, design, installation, cable termination, protective coordination, testing, labeling and acceptance. A contract may assign different aspects to different parties; the register must not imply that every aspect of a physical asset belongs to whoever supplies its hardware.
Start from the single-line diagram rather than the organization chart. Identify the electricity seller’s metering/PCC interface, MV owner boundary, RMU/transformer supply scope, LV bus and feeder circuits, distribution boards, machine incomers, BMS/SCADA communications, earthing/PE continuity, and integrated tests. For a new factory, add the civil interface for transformer foundations, trenches, wall openings and cable risers. For a brownfield factory, add existing-system ownership, planned shutdown windows and conditions for restoration of service. Treat site access, lifting and energized-work constraints as delivery interfaces, not invisible preliminaries.
| Interface ID | Exact boundary | Typical unresolved choice | Document that should close it |
|---|---|---|---|
| I-01 | Electricity seller to client’s MV incoming point | Who supplies revenue metering, CT/VT, cubicle and seals? | Named connection and metering agreement |
| I-02 | MV switching to transformer terminations | Supplied cable and test ownership? | SLD, MV termination schedule and witness test plan |
| I-03 | Transformer to MSB | Busduct or parallel single-core cables, actual length? | Approved route, termination and LV feeder design |
| I-04 | MSB outgoing feeder to OEM machine incomer | Cable lugs, gland plate and isolation by whom? | Vendor terminal drawing and interface responsibility table |
| I-05 | Generator/ATS/UPS to emergency board | Transfer controls, neutral/PE path and safe-stop sequence? | Functional specification, interlock drawing and test script |
| I-06 | Civil foundation to equipment anchors | Embedment, loads, tolerance and lifting access? | Civil/equipment coordinated drawing and inspection hold point |
| I-07 | SCADA/EMS meter to network | Tag naming, time synchronization, protocol and data ownership? | Points list, cyber/access matrix and FAT/SAT records |
The source of authority matters. The landlord, factory owner, EPC, distribution utility and equipment supplier may each control different interfaces. A register cannot assign authority on their behalf when contracts or approved documents say otherwise. Label an unresolved allocation PROPOSED, not APPROVED, and record who is required to make the decision.
Minimum columns that make an interface register actionable
A robust row includes: unique interface ID; system/area; upstream and downstream package; drawing and revision; physical boundary; required technical data; producer; reviewer; contractual approver; downstream consumer; required date; status; decision; evidence link; residual assumption; change event and last update. Additional columns can track tag numbers, source type, safety criticality and testing witness. Avoid placing dozens of possible questions in free-text cells without a responsible person or due date: the register becomes a list nobody can close.
| Field | Example value in a fictitious factory | Reason for inclusion |
|---|---|---|
| Interface ID | IF-LV-017 | Stable key for RFI and commissioning references |
| Boundary | LV MSB Feeder F08 → OEM Panel M-12 incoming lugs | Measurable physical point |
| Producer | Electrical EPC for cable; OEM for terminal details | Distinguishes two deliverables |
| Checker | Factory electrical engineering lead | Independent consistency check |
| Acceptance owner | Owner-appointed engineer under contract | Prevents self-certification by default |
| Linked drawings | E-SLD-004 Rev C; OEM-M12-020 Rev B | Revision control |
| Required data | Rated/starting current, neutral, earthing, terminals | Enables final design |
| Hold point | Before cable procurement and wall closure | Controls irreversible work |
| Status | OPEN — OEM cable gland detail missing | Honest readiness marker |
| Evidence to close | Signed RFI answer and updated cable schedule | Auditable decision trace |
Use a finite status vocabulary: OPEN, INPUT_RECEIVED, UNDER_TECHNICAL_REVIEW, APPROVED_WITH_ACTIONS, CLOSED, REOPENED_AFTER_CHANGE. The last status matters: an OEM changes machine current or terminal location after IFC drawings are released, and yesterday’s closed boundary can become wrong. An audit trail should preserve who closed it and which revision made that close-out valid.

Worked interface: a production machine supplied at 400 V
Assume an OEM machine has a three-phase 400 V incoming panel rated at 160 A, with a 25-metre intended cable route from an existing factory MDB. The two parties agree only that “power will be brought to the machine”. Nothing yet states whether the OEM has a neutral requirement, the terminal bar accepts two parallel conductors, the machine has a built-in main isolator, the protection device must have a specific characteristic, or the cable entry is top or bottom. A tender that locks the cable cross-section now is not only uncertain in price—it risks a physical installation that cannot terminate safely.
At an idealized balanced power factor of 0.90, the electrical active power corresponding to 160 A at 400 V would be P = sqrt(3) × 400 × 160 × 0.90 / 1000 ≈ 99.8 kW, with apparent power S ≈ 110.9 kVA. This is a simple arithmetic check to make the interface scale intelligible. It does not establish that the machine will actually draw that steady current, nor specify its inrush, harmonic spectrum, cable grouping, conductor temperature rating or short-circuit protection. The input 160 A is a stated fictional panel rating, not evidence that 160 A is its measured operating demand.
The physical length and purchased conductor length must also be distinguished. A 25-metre route may require a three-phase and neutral system plus separate PE depending on the approved design, different termination allowances, spare length and different cross-sectional selections. The theoretical conductor quantity is route length × number of required conductors/runs; a 25 m route does not mean that a procurement line for multiple single-core conductors should order only 25 m total. The detailed conductor take-off cannot be finalised until the actual number and arrangement of conductors, routing, grouping, voltage drop and fault/earthing conditions are approved.
The appropriate response is a short interface RFI with evidence fields: (1) confirm full-load/maximum input current and starting behaviour; (2) confirm neutral and PE topology; (3) provide exact terminal/gland drawing with lug sizes and direction of entry; (4) identify main isolator and upstream protective coordination requirement; (5) declare earthing/EMC requirements; (6) confirm responsibility for termination tests and first energization. Each question has a recipient and decision deadline, not a blanket “contractor to verify on site”.
Interface engineering is not only about equipment—it changes the schedule
Late interface decisions can generate rework that is more expensive than the component itself. If the civil contractor casts a plinth before receiving verified transformer footprint and anchor data, a later vendor change may require demolition or redesign. If cable routes are closed before machine coordinates are frozen, feeder length and termination locations can change. If utility ownership is unresolved until energization week, even technically complete equipment may not be operable. Put the work-package dependency into the register so a decision is due before an irreversible activity.
| Milestone | Required input | Hold point | What may proceed if not closed |
|---|---|---|---|
| H01 design freeze | Confirmed supply and machine data | Sign interface basis | Feasibility only; no final cable procurement |
| H02 civil pour | Approved transformer/panel dimensions, loads and openings | Civil/electrical joint inspection | Preparatory civil work outside constrained area only |
| H03 cable order | Approved sections, routes, conductor/runs and termini | Quantity and technical release | Reserve generic procurement capacity only |
| H04 assembly FAT | Approved interlocks, schemes and acceptance plan | Witness/approval of outstanding items | Shipment subject to contractual release |
| H05 electrical SAT | Completed installation, calibration and inspection | Site test sign-off | No energization solely on the basis of schedule pressure |
| H06 grid/plant power-on | Actual seller/owner authorizations and site readiness | Authorized switching/commissioning record | Plan cannot substitute for permission |
These are illustrative work packages, not guaranteed durations or statutory approval steps. Actual local electricity connection arrangements, contracts, competent parties and applicable Vietnamese requirements must be confirmed separately. A contractor cannot legitimately solve a missing approval by simply assigning it to itself in a spreadsheet.

Turn the register into RFQ and change-control discipline
The register should accompany the BOQ. Give bidders the same current drawing revisions and the same open questions. Request pricing both for a confirmed baseline and for separately identified provisional items where the scope is genuinely unknown. A provisional cable route, unidentified CT chamber, unknown incoming panel terminal or uncertain night shutdown should be labelled provisional and linked to a measurable adjustment mechanism. Comparing a cheap quotation with unlimited exclusions against a complete quotation is not a meaningful tender evaluation.
Changes after award should state which interface ID moved, which design documents changed, whether equipment has been manufactured, the effect on safety/protection tests, expected cost/time consequence and who authorized the change. An “approved” drawing is not permanent if a machine vendor issues a changed rev after procurement. In that case, reopen the interface, assess the affected cable/CB/protection or control and obtain a new close-out record before the work advances.
Digital tools can support this process, but a detailed platform is not essential. A controlled spreadsheet with IDs, owners, drawing links, dated decisions and a weekly action meeting often suffices for a smaller package. Larger EPC programs may integrate the same fields into a document management and RFI workflow. What matters is a consistent single owner for each decision, not necessarily one contractor performing all the work.
Quality checks, examples of errors and resolution paths
One recurring failure is to record CLOSED when the owner merely acknowledges receipt of a supplier email. Receipt is not technical acceptance. Another is to place a generic diagram under the equipment boundary, then later discover that the terminal height or bending space differs from the purchased cabinet. A third is to treat a successful transformer insulation test as proof that downstream machine protection has been fully coordinated. Those are separate technical deliverables with different evidence and test conditions.
For each critical interface, verify that the diagram tag exists physically, the latest document is known, the recorded producer and checker are real and the acceptance record corresponds to the specific revision. Reinspect high-risk rows after site changes, especially live-plant cutovers or changes to supply owner boundaries. Keep civil/electrical, data/electrical and OEM/EPC boundaries visible instead of reporting only overall percent completion.
If a dispute arises, the register should show what was requested, what was provided, what was accepted and under which contract or design basis the decision was made. It should not pretend to amend legal contract allocations on its own. A technical interface row is useful evidence for project management; the signed contract and applicable legal approvals still govern responsibilities.

References and applicability
| Reference / evidence class | Intended scope | Verification limit on 10 October 2026 |
|---|---|---|
| IEC 60364-5-52:2009+A1:2024 | LV conductor/wiring installation considerations | Official catalogue edition/scope; actual cable design requires project data |
| IEC 60076-1:2011 | General transformer specifications | Official catalogue; transformer civil drawings from actual vendor required |
| IEC 60909-0:2026 | AC short-circuit calculation scope | Official current edition metadata; not an executed fault study |
| OEM/ATS/SCADA/relay manuals | Termination, communications, control and operating modes | Exact supplier revision must be supplied and checked |
| Applicable Vietnamese connection, safety and project contracts | Who owns assets and authorizes works at named site | Cannot be assigned from a generic article; obtain actual agreements |
Related resources and next action
For the high-level allocation see Who owns each electrical design deliverable?. For comparable scope in bidding, use What are you really buying in an electrical EPC tender?. For procurement sequencing consult Long-lead electrical equipment: plan a factory schedule. Each addresses a different part of the project decision, while the interface register connects them at the equipment boundaries.
The QuangAnhcons substation commissioning archive video illustrates practical site work and energization context; it does not prove the boundary allocations in this fictional example.
An owner preparing a split-package electrical RFQ can send the latest SLD, package list, OEM machine drawings, scope notes and open interface questions to projects@quanganhcons.com or +84 919 758 191. QuangAnhcons can discuss a defined scope-review and BOQ preparation service without claiming that unapproved project responsibilities have already been assigned.
[contact-form-7 id="7239967" title="Contact form 1"]Substation budget estimate
Select the capacity, route lengths and package to view your indicative budget and electrical parameters.
Request a project quotation
Send your project details, BOQ or drawings to request a formal quotation. Fields marked * are required.
Quotation scope
Applies to one EVN-supplied substation with oil-immersed transformers at 22/0.4 kV (single-phase: 12.7/0.23 kV), with MV metering VTs/CTs supplied by EVN. The estimate includes the selected equipment, installation, earthing, transformer-to-main-breaker connections, design and connection documentation, and coordination of testing and utility acceptance.
Kiosk, integrated steel-pole and indoor substations include MV switchgear and the entered underground cable route. Other outdoor arrangements use the relevant protection configuration. The final diagram must meet the project connection requirements.
Excludes VAT, cables from the substation switchboard to the MSB/loads, live-line work, harmonic reactors, weak-ground treatment or special piling, land and special fire-protection provisions. Underground routes assume normal construction conditions and exclude road drilling and special reinstatement.
Prices are indicative investment budgets. A formal quotation follows site assessment and agreement on the configuration. Electrical selections are preliminary and require design verification before installation.
Capacity range and application conditions
The catalogue defines the enquiry range of this tool, not universal TCVN capacity limits. Single pole-mounted transformers: 15–100 kVA; three-unit banks: 3×15–3×100 kVA. Platform substations: 100–630 kVA. Steel-pole substations: 100–630 kVA; 750/800 kVA require design verification and local approval. Ground-mounted, kiosk and indoor configurations: 50–10,000 kVA. Not every configuration has a package price or the same structural design.
Reference: EVN Decision 1299/QD-EVN dated 3 November 2017, Volume 1, sections 3.3–3.4. Check the current requirements of the responsible utility before implementation. Kiosks must meet manufacturer ratings and testing requirements (IEC 62271-202); indoor and ground-mounted arrangements must meet project layout, ventilation, structural and fire-protection requirements. For multiple transformers, specify the quantity and capacity of each unit.
Developed by QuangAnhcons · © 2026 QuangAnhcons. Code licensed under GPL-2.0-or-later. Standards and manufacturer data belong to their respective owners.



Related Posts
Factory electrical interface register: close MV/LV and OEM boundaries before procurement
A project-ready electrical interface register connects the utility, transformer, MSB, OEM machines, civil works and [...]
Oct
Harmonics in Transmission and Distribution Power Systems: From 500 kV to End-Use Loads
A rigorous power-quality monograph from 500 kV transmission to end-use equipment, covering Fourier spectra, symmetrical [...]
BESS end-of-warranty acceptance: contract for net AC-deliverable energy
Define BESS end-of-warranty capacity at a named AC meter, not an ambiguous DC nameplate; includes [...]
Oct
Size an industrial standby generator from essential-load steps, not transformer kVA
A factory standby-generator procurement guide with a worked six-group P/Q load example, transfer sequence, motor-start [...]
Oct
Before choosing breaker kA ratings: build a complete factory fault-case register
An electrical fault-case register separates maximum breaking duty from minimum-fault protection sensitivity, with documented grid, [...]
Oct
Imported production lines: turn motor ratings into an auditable factory P/Q load schedule
A worked industrial load schedule converts imported machine shaft kW to active and reactive demand, [...]
Oct
Long-Lead Electrical Equipment: Plan a Vietnam Factory Schedule
Plan long-lead electrical equipment for a Vietnam factory with release milestones, a backward schedule, site [...]
Oct
Who Owns Each Electrical Design Deliverable? A Responsibility Matrix for FDI Factories
Build an electrical design responsibility matrix for a Vietnam factory. Assign inputs, checks and approvals [...]
Oct
Before Leasing a Factory in Vietnam: Verify the Electrical Supply
Verify capacity, condition and landlord–tenant boundaries before leasing a factory in Vietnam. Use an evidence [...]
Oct
What Are You Really Buying in an Electrical EPC Tender?
Compare electrical EPC tender offers fairly. Use a scope matrix, worked bid example, RFQ wording [...]
Oct
Who Owns the Utility Connection? Responsibilities in a Vietnam Factory EPC Project
A decision guide for FDI factory owners in Vietnam: divide utility connection responsibilities among the [...]
May
Professional Electrical System Installation Process in Vietnam
As Vietnam’s industrial and urban sectors continue to grow, the need for reliable electrical system [...]
Aug
Find the Best Electrical Contractor Near Me – Your Reliable Partner
Finding a dependable electrical contractor near you is crucial for ensuring the safety and efficiency [...]
Jul
Top Vietnam Electrical Contractor Near You – QuangAnhcons
Finding a reliable electrical contractor is crucial for ensuring the safety and efficiency of your [...]
Jul
Top Vietnam Electrical Contractor Services – Choose QuangAnhcons
When it comes to ensuring the electrical safety and efficiency of your industrial facilities, finding [...]
Jul
Expert MEP Engineering for Industrial Buildings – QuangAnhcons
Efficient MEP (Mechanical, Electrical, and Plumbing) engineering is crucial for the optimal performance of industrial [...]
Jul
Trusted Electrical Contractors – Your Partner in Industrial MEP Solutions
In the rapidly evolving industrial sector, finding reliable MEP contractors is crucial. QuangAnhcons stands out [...]
Jul
MEP Construction Services for Factories – Comprehensive Solutions for Businesses
In the context of modern industry, MEP (Mechanical, Electrical, and Plumbing) construction services for factories [...]
Jul
Top-Notch Industrial Electrical Installation Services
Ensuring the optimal functioning of electrical systems in industrial settings is crucial for operational efficiency [...]
Jul
Professional Low Voltage Electrical Cable Installation and Cable Tray Construction – Enhancing Safety and Aesthetics
Upgrading your electrical systems is crucial for ensuring safety, efficiency, and aesthetics in any industrial [...]
Jul