Short answer: do not compare industrial sites only by the power capacity written in a brochure or utility letter. Compare the complete electrical delivery path: the party that owns the connection, available capacity and firm date, voltage level, route and land rights, substation footprint, outage constraints, fault-level data, power-quality exposure, redundancy, metering boundary, expansion path and the evidence behind every claim.
This guide is for FDI investors, factory owners, project managers and EPC teams screening sites in Vietnam. It is a due-diligence framework, not a utility commitment, connection approval, legal opinion or electrical design. Every capacity, date and interface must be confirmed with the relevant industrial-park operator, electricity entity, landlord and competent authorities for the actual site.
Start with the load case, not the site brochure
A site comparison is only meaningful when all candidates are tested against the same operating case. Prepare a short load-basis sheet before requesting site data:
- production-line connected load and operating sequence;
- HVAC, process cooling, compressed air, water and utility loads;
- life-safety, emergency and business-continuity loads;
- large motors, furnaces, welders, rectifiers, drives and other disturbance-producing loads;
- planned rooftop solar, BESS, EV charging and generator interfaces;
- commissioning, ramp-up and later expansion stages;
- required availability, maintainability and permitted production interruptions.
Separate connected load, coincident maximum demand, standby load and future load. Do not subtract expected PV production from the firm import requirement unless the operating concept, grid rules, control scheme and contractual supply basis make that reduction dependable.
Use one evidence register for every candidate site
| Decision field | Evidence to request | Do not accept as proof |
|---|---|---|
| Available capacity | Named supply point, voltage, existing committed load, firm allocation process and validity date | A marketing brochure stating “high-capacity power” |
| Energization date | Responsibility matrix, design approvals, permits, equipment lead times, route access and tested programme | An unsupported target month |
| Connection route | Surveyed alignment, crossing list, land/access rights, interfaces and construction constraints | A straight line drawn on a master plan |
| Network strength | Utility-approved short-circuit and impedance data at the agreed point and date | Breaker kA ratings copied from another tenant |
| Reliability | Source arrangement, switching authority, restoration method, maintenance outage history and agreed service boundary | “Dual supply” without independent route and operating detail |
| Expansion | Reserved bay/route/land, transformer and switchgear strategy, protection-study path and commercial release trigger | An empty space labelled “future” |
Confirm who owns each electrical interface
The same physical site can produce very different risk depending on the ownership boundary. Identify who designs, pays for, constructs, tests, owns, operates and maintains:
- the upstream line or cable and any dedicated feeder;
- the revenue-metering installation and communication path;
- MV switchgear, protection, control and earthing interfaces;
- transformers and the factory LV distribution;
- route easements, road crossings and temporary works;
- future uprating or second-source works.
Record the document that creates each responsibility: lease, connection agreement, industrial-park service agreement, utility instruction, approved design or EPC contract. The utility-connection responsibility guide provides a more detailed interface matrix.
Screen capacity with transparent assumptions
Consider an illustrative factory load case used only to compare data requests. It is not an approved design basis:
- production coincident active demand: 3.60 MW;
- MEP and process utilities: 0.45 MW;
- other coincident loads: 0.18 MW;
- screening power factor: 0.95;
- future active-load step, assessed separately: 0.90 MW.
The current screening demand is:
P = 3.60 + 0.45 + 0.18 = 4.23 MW
The corresponding apparent-power screen is:
S = P / PF = 4.23 / 0.95 = 4.45 MVA
For a balanced three-phase screening calculation, the line current would be approximately:
I = S / (√3 × U)
- at 11 kV:
I = 4.45 MVA / (√3 × 11 kV) ≈ 234 A; - at 22 kV:
I = 4.45 MVA / (√3 × 22 kV) ≈ 117 A.
The arithmetic check is consistent because doubling voltage halves current for the same apparent power. It does not select a voltage, feeder, cable, transformer or breaker. Actual selection still requires load profiles, motor starting, harmonics, route and installation method, ambient conditions, voltage regulation, losses, protection, minimum and maximum fault levels, utility criteria and approved redundancy philosophy. The future 0.90 MW step adds about 0.90 / 0.95 = 0.95 MVA under the same illustrative assumption; it should not be hidden inside an undefined percentage reserve.
Compare the connection programme as a critical path
A capacity statement without a deliverable date is incomplete. Build the programme backward from required production energization and identify:
- load-data freeze and connection application;
- survey and agreed connection point;
- responsibility and commercial approvals;
- system studies and protection-data release;
- route, land, crossing and environmental permissions where applicable;
- design approval and equipment technical release;
- manufacture, FAT, delivery and civil readiness;
- installation, pre-commissioning and integrated testing;
- metering, protection witness, energization and production ramp-up.
Assign an owner and evidence date to every milestone. A site with nominally more capacity may be the weaker choice if the route, approval or equipment path cannot meet the factory programme. Use the long-lead equipment release guide to test whether the proposed date is achievable.
Do not confuse two incomers with resilient supply
For each claimed source, draw a simple supply-path diagram from the upstream network to the production bus. Ask whether the paths share the same upstream substation, trench, cable bridge, switchboard section, protection system or operating team. Define the credible single failures and the permitted switching time.
Then separate:
- firm utility capacity under normal network conditions;
- operating redundancy that the connection agreement actually permits;
- factory standby supplied by generator, UPS or BESS;
- process ride-through required for sensitive production steps.
A second incomer that cannot be paralleled, lacks spare transformer capacity or shares one vulnerable route may improve restoration options without delivering full N−1 production capacity.
Request network data before equipment selection
Site comparison should flag whether usable study data will be available at the agreed point of connection. IEC 60909-0:2026 provides a method for calculating short-circuit currents in three-phase AC systems within its stated scope. It does not supply the project-specific network model. The owner still needs the relevant source impedances, operating cases, transformer data, conductor data and contribution from rotating or converter-connected sources.
Compare the candidate sites on:
- maximum and minimum fault cases available for protection and equipment studies;
- voltage limits and expected operating range at the connection point;
- protection ownership, settings approval and grading interfaces;
- earthing data and boundary responsibilities;
- harmonic, flicker, unbalance and rapid-load-change constraints;
- metering accuracy, data access and event-record availability.
Do not infer a permissible breaker rating from a neighboring tenant. The factory fault-case register explains why equipment selection requires more than one headline fault value.
Check route, room and expansion geometry
Electrical infrastructure uses land and access long after construction. Confirm:
- substation room or outdoor compound dimensions and fire/access boundaries;
- transformer replacement path, crane position and delivery turning radius;
- cable trench, duct-bank and crossing capacity;
- separation from drainage, process utilities, hazardous zones and future buildings;
- flood level, corrosion exposure, ventilation and heat-rejection constraints;
- space for switchgear extension without unsafe live work;
- future solar, BESS, EV and generator connection points.
A future bay is useful only when the bus rating, protection architecture, physical clearance, cable route and upstream capacity can support it. The substation delivery-access guide provides a field evidence checklist.
Use a weighted comparison, but keep vetoes separate
| Criterion | Illustrative weight | Minimum evidence |
|---|---|---|
| Firm capacity and connection boundary | 25% | Dated allocation path and named connection point |
| Energization critical path | 20% | Owner, dependencies and evidence for each milestone |
| Reliability and restoration | 15% | Supply-path diagram and operating constraints |
| Route, land and construction access | 15% | Surveyed route and rights/interface register |
| Network data and power quality | 10% | Study-data release plan and responsibility |
| Expansion and decarbonization interfaces | 10% | Reserved capacity, route and control concept |
| Operations, metering and outage coordination | 5% | Draft operating and data-access matrix |
These weights are illustrative. A factory may apply hard vetoes before scoring—for example, an energization date later than the equipment-installation window, no safe transformer replacement route, or no credible supply for a safety-critical process. Do not let a high score in low-risk categories offset a fatal constraint.
Include an electrical due-diligence BOQ
| Work item | Deliverable | Decision supported |
|---|---|---|
| Load workshop | Connected, coincident, standby and phased load register | Common comparison basis |
| Connection review | Interface and responsibility matrix | Scope, owner and contractual gap |
| Route survey | Alignment, crossings, access and constraint register | Feasibility and programme |
| Preliminary power-system screen | Voltage, load flow, fault-data request and study-case list | Data sufficiency and design risk |
| Reliability workshop | Supply-path and credible-failure matrix | Downtime and standby strategy |
| Expansion review | Land, bay, route, control and capacity reserve register | Future-stage feasibility |
| Decision report | Evidence score, vetoes, open items, owners and deadlines | Investment approval |
FAQ
Is an industrial-park capacity letter enough?
No. It is one input. Confirm the exact connection point, voltage, committed capacity, validity, allocation procedure, project responsibilities, route and achievable energization date.
Should the site with the highest voltage be preferred?
Not automatically. Voltage affects current, equipment and connection architecture, but site selection must also consider network data, route, programme, reliability, ownership and expansion. The approved design determines the appropriate solution.
Can rooftop solar reduce the required utility connection?
It may reduce daytime energy import, but output varies and may not coincide with the factory peak. Treat any firm-capacity reduction only through an approved operating and control basis supported by the actual load and generation profiles.
How should future expansion be handled?
Show it as a separate load stage with a release date and enabling works. Verify upstream capacity, switchgear and transformer strategy, protection studies, land, access and cable routes rather than applying an unexplained reserve percentage.
What should remain open at land or lease approval?
Open items may remain, but each needs an owner, evidence request, deadline, decision consequence and contractual protection. Unknown is not the same as acceptable.
Decision checklist
- All candidates use the same load and production assumptions.
- Capacity, voltage, point of connection and validity are documented.
- Connection ownership and payment boundaries are explicit.
- Route, rights, crossings and construction access are surveyed.
- Fault, voltage, protection and power-quality data have a release path.
- Reliability claims are tested through common-mode failures.
- Energization is a resource-loaded critical path, not a target date.
- Substation, replacement and future-expansion geometry is workable.
- Solar, BESS, EV and generator interfaces are included without double counting.
- Every unresolved item has an owner, deadline and investment consequence.
Conclusion
An electrically suitable industrial site is not the site with the largest advertised number. It is the site whose capacity, connection route, ownership, programme, network data, reliability and expansion path are supported by evidence and fit the factory operating case. Build one comparable evidence register, apply hard vetoes before weighted scoring, and carry unresolved constraints into the lease, connection and EPC documents.
For a site-specific review, prepare the production load list, target energization date, candidate master plans, connection correspondence, route drawings, lease/service terms and expansion scenario. QuangAnhcons can structure an owner-side electrical due-diligence matrix from those inputs; final utility commitments, design and approvals remain project-specific.
Primary references
- IEC 60909-0:2026 — official IEC catalogue scope for short-circuit current calculations in three-phase AC systems.
- IEC 60364-5-52:2009+AMD1:2024 CSV — official IEC catalogue scope for selection and erection of wiring systems; project adoption remains to be confirmed.
- IFC Sustainability Framework — official framework for risk and impact identification, including associated facilities and project location considerations.
- World Bank Group Eco-Industrial Park Practitioner’s Handbook — official implementation resource for industrial-park planning and performance.
Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
Comparing Industrial Sites by Power Infrastructure Constraints
Compare factory sites using firm capacity, connection route, ownership, energization, fault data, reliability and expansion [...]
Provisional Quantities in Factory Electrical Tenders: Define the Rule Before Pricing
Define provisional electrical quantities with measurable units, release triggers, unit-rate inclusions, joint records and a [...]
Electrical Thermography Reports: What a Factory Owner Must Receive
Define a useful electrical thermography report for a Vietnam factory: asset identity, operating load, camera [...]
Backup Power Acceptance Tests: A Production-Safe Factory Plan
Plan generator and ATS acceptance around production constraints, with a controlled test sequence, P/Q load [...]
EV Charging Load Management: Requirements for a Corporate Fleet RFQ
Define site power caps, fleet priorities, offline behaviour, data, BOQ and scenario-based acceptance tests for [...]
BESS Supplier Safety Documentation: An Owner’s RFQ and Acceptance Register
A configuration-specific BESS safety-document register for RFQ, design review, FAT, SAT, change control and owner [...]
Factory Rooftop Solar Installation: Plan the Work Around Production, Not Across It
Build a rooftop PV installation plan around factory production, with roof zones, permits, lifting, isolation [...]
Factory Electrical Spare Capacity: Define What 20% Means Before Tender Award
Turn a vague 20% electrical spare-capacity promise into measurable demand, thermal, fault-duty, physical-space and expansion-interface [...]
Manufacturer Certificates vs Site Test Evidence: What an FDI Owner Should Accept
Separate manufacturer certificates, factory test records and site commissioning evidence with a traceable acceptance matrix [...]
Electrical Equipment Storage Before Installation: A Release Matrix for Vietnam Factory Projects
Define storage, preservation and release controls for MV/LV switchgear, transformers, cables and auxiliaries before electrical [...]
Design Freeze Milestones for Factory Electrical Procurement: What Must Be Fixed Before Release
Freeze the right electrical design inputs before factory procurement: ratings, MV/LV interfaces, vendor documents, hold [...]
Rooftop PV Export-Limit Commissioning: Prove the Control at the Grid Meter
Commission a rooftop PV export-limit scheme at the point of connection with CT checks, load-drop [...]
BESS Auxiliary Load and Temperature Derating: A Site Acceptance Test for Net Performance
Test BESS net AC energy, standby auxiliaries, HVAC demand and temperature derating with explicit meter [...]
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]