Short answer: a provisional quantity is not permission to issue a vague electrical tender. It is a controlled placeholder for work whose physical quantity cannot yet be measured with reasonable confidence. The tender must still define the item, unit, measurement boundary, unit-rate inclusions, survey trigger, approval route and evidence needed to convert the placeholder into a final measured quantity.
This guide is for FDI factory owners, project managers, consultants and EPC bidders preparing an industrial electrical tender in Vietnam. It explains a procurement method; it does not replace the signed contract, Vietnamese law, the approved design, utility requirements or project-specific legal advice.
Separate four commercial ideas before pricing
Many disputes begin because one BOQ column mixes four different concepts:
| Concept | What it means in this guide | Required tender treatment |
|---|---|---|
| Fixed quantity | The design and survey support a defined quantity at tender issue. | Price the stated quantity under the declared measurement rule. |
| Provisional quantity | The item is defined, but part of its physical quantity remains uncertain until a named survey, vendor release or access event. | Show the provisional portion separately, with a measurable unit and a usable unit rate. |
| Provisional sum | A monetary allowance controlled by the contract for a defined scope or contingency. | State who may instruct its use, how value is evidenced and whether attendance, overhead and profit are included. |
| Contractor risk allowance | An amount a bidder includes for ordinary execution risk within a firm scope. | Do not hide it inside a remeasurable quantity or count it again as a provisional sum. |
The exact legal effect of these labels depends on the contract. The World Bank’s public procurement framework provides standard procurement documents, and an older public sample works document illustrates provisional sums as designated BOQ amounts used only under the contract administrator’s instruction. A private factory tender should not copy that wording blindly, but it should achieve the same clarity: one defined authority, one valuation rule and an auditable instruction.
Use provisional quantities only for a named uncertainty
A legitimate uncertainty has an owner, a release event and a date. Examples may include:
- an existing underground duct route that cannot be surveyed until an operating-area shutdown;
- final drops to imported production machines whose certified connection drawings are due after tender;
- cable-tray diversions around process services that will be frozen during coordinated shop drawings;
- earthing-electrode extensions whose need depends on field measurements and the approved earthing design;
- fire stopping at penetrations that cannot be counted until builders’ openings are released;
- night-shift access or temporary power that depends on the owner’s production window.
“Design incomplete” is not an adequate uncertainty register. The tender should identify which drawing, survey or vendor document will close each gap. If equipment ratings, feeder count, room layout or system responsibility are not defined, the issue may be a design-basis hold rather than a provisional quantity. The related electrical design-freeze guide explains which inputs should be fixed before a purchase release.
Do not make known scope provisional
Known obligations should remain in the base scope. Examples include preparing shop drawings, coordinating ordinary supports, providing standard labels, submitting test records, protecting completed work and correcting contractor-caused defects. Making these items provisional can make bids look artificially low and creates an approval burden during construction.
Likewise, a bidder should not convert a clearly specified package into a lump-sum exclusion merely because its detailed take-off differs from the owner’s estimate. The tender must say whether the owner’s quantity is contractual, indicative for bid comparison, or remeasurable. The broader electrical EPC tender-boundary guide can be used to separate supply, installation, testing and interface ownership before quantities are compared.
Create a quantity-basis sheet for every provisional line
| Field | What the owner should state | Bidder return |
|---|---|---|
| BOQ code and description | System, location, material and performance boundary | Confirmation or listed qualification |
| Measurement unit | Route metre, conductor-metre, each, set, point, square metre or another defined unit | Unit rate in the same unit |
| Reference quantity | Measured base plus separately identified provisional portion | Independent take-off and variance note |
| Source information | Drawing revision, survey date, model or vendor-data reference | Assumptions used where information is absent |
| Inclusions | Fittings, supports, waste, access, testing, labels, documentation and disposal as applicable | Explicit included and excluded items |
| Release trigger | Survey, approved shop drawing, vendor interface or site instruction | Required lead time and effect on programme |
| Measurement evidence | Joint measurement, marked-up drawing, delivery record or test sheet | Proposed record format and responsible person |
| Valuation rule | Unit-rate application, new-rate procedure or instructed lump sum | Rate build-up and validity conditions |
The existing electrical survey and BOQ page is a useful starting point for collecting route, room and interface evidence before the tender is issued.
Define electrical measurement units without ambiguity
Route metre is not conductor-metre
A 100 m route carrying four single-core conductors is 100 route-metres but 400 conductor-metres before any separately defined termination allowance. If the BOQ states only “cable, m,” two bidders may price different quantities while both believe they complied.
“Set” needs a boundary
A switchboard “set” should identify sections, incomers, bus couplers, outgoing devices, protection, metering, control power, internal wiring, inter-panel links, base frames, accessories, factory tests and documents. A provisional number of feeders can be priced per feeder only if the feeder type, current range, fault duty, control interface and spare-space effect are defined.
Terminations need equipment interfaces
MV and LV termination items should distinguish cable construction, voltage class, conductor size and material, number of cores, indoor/outdoor interface, equipment connection and testing. Do not assume a termination rate remains valid after the cable or switchgear interface changes.
Testing is not automatically included in installation
The BOQ should say which inspections, initial verification, functional tests and records accompany each measured item. IEC 60364-6:2016 covers initial and periodic verification of low-voltage installations; it does not create a universal commercial measurement rule. Use the approved project inspection and test plan to define the actual test boundary and acceptance evidence.
Worked take-off: check route and conductor quantities independently
Consider a hypothetical feeder route prepared only to demonstrate quantity logic. It is not a cable-sizing recommendation or project record.
- Horizontal route from LV board to machine area: 132 m.
- Vertical rises and drops: 18 m.
- Explicit service-loop and entry length: 8 m.
- One conductor per phase plus one protective conductor: four conductors along the same route.
- Unsurveyed corridor extension released later: 22 route-metres.
The tender-reference route is:
132 m + 18 m + 8 m = 158 route-m
The tender-reference conductor quantity is:
158 route-m × 4 conductors = 632 conductor-m
After the corridor is surveyed, the revised route becomes:
158 m + 22 m = 180 route-m
The corresponding conductor quantity is:
180 route-m × 4 = 720 conductor-m
An independent delta check gives the same result:
22 m × 4 = 88 conductor-m; 632 + 88 = 720 conductor-m
The provisional line should therefore identify 22 route-metres and its effect on four conductors, not add an unexplained percentage to a cable quantity. Any installation waste, drum constraint, spare length or jointing allowance must be justified and shown separately; this example does not prescribe one.
Build the BOQ around decisions and evidence
| Electrical package | Useful unit | Typical uncertainty trigger | Close-out evidence |
|---|---|---|---|
| Cable tray or ladder | Route metre by width, depth, finish and loading class | Coordinated route and support-zone release | Approved shop drawing and joint route measurement |
| MV/LV cable | Conductor-metre or cable-metre with construction stated | Final route, drum plan and equipment entry | Drum schedule, installed route, joint/termination register and test pack |
| Conduit and small power | Route metre and point by system | Final machine or workstation layout | Marked-up layout, point schedule and verification record |
| Switchboard feeders | Each by feeder functional specification | Final motor/equipment list and protection study | Approved schedule, FAT record and final settings |
| Earthing extensions | Metre or each by conductor/electrode type | Approved design and field measurement | As-built grid, connection inspection and test results |
| Fire stopping | Each or area by tested system and opening type | Final penetration register | Location register, approved system evidence and inspection record |
Product standards help define the equipment being priced, not the commercial quantity rule. IEC 61439-2:2020 applies to power switchgear and controlgear assemblies within its stated LV scope. IEC 62271-200:2021, together with Amendment 1:2024, covers AC metal-enclosed switchgear within its stated voltage scope. Reference only the editions and requirements selected by the project; do not write “IEC compliant” without mapped evidence.
Use a five-step release workflow
- Tender issue: publish the quantity-basis sheet, drawings, uncertainty register and common return template.
- Bid clarification: normalize bidder assumptions and reject double counting between fixed, provisional and excluded scope.
- Post-award survey: record actual dimensions and interfaces jointly before ordering affected materials.
- Instruction and valuation: use the named contract authority and the agreed rate or new-rate process before work proceeds, except for separately defined emergency controls.
- Close-out: reconcile tender, instructed, installed and accepted quantities against as-built and test records.
The electrical ITP guide can help assign review, witness and hold points. For owner-supplied packages, align quantity release with the custody and acceptance matrix.
Prevent double counting in bid comparison
Ask bidders to return the same reconciliation:
- base quantity from owner documents;
- bidder-measured correction to that base;
- provisional quantity priced at a visible unit rate;
- fixed accessories and obligations included in the rate;
- excluded work and the document needed to price it;
- programme, shutdown and access assumptions;
- tax, escalation and currency treatment where commercially applicable.
A low tender can otherwise result from excluding fittings, supports, testing or access rather than from a more efficient solution. Keep commercial evaluation separate from technical compliance, and do not publish bidder prices or internal negotiation data.
HSE and construction controls remain mandatory
A provisional quantity does not make the associated work optional from a safety perspective. Cable-route surveys, opening of electrical rooms, work near energized systems, lifting, work at height, excavation and fire-stopping inspections need the approved method statement, permits, isolation boundaries and competent personnel applicable to the site. Quantity confirmation must not require unsafe live access. If the area cannot be surveyed safely before award, state the restriction and the controlled post-award survey window.
FAQ
Should every uncertain item use a provisional sum?
No. If the work item and unit rate can be defined, a provisional physical quantity may be more transparent. A monetary provisional sum is useful only when its scope, instruction and valuation controls are clear under the chosen contract.
Can an owner add a blanket ten percent to every cable?
That is weak procurement practice unless the percentage has a documented physical basis. Show route geometry, conductor count, known service loops and the precise unknown segment. Keep drum optimization and installation waste as separately explained assumptions.
What if the bidder’s take-off differs from the owner’s quantity?
Require a marked-up take-off and reconcile the drawing revision, measurement unit and inclusions. The tender must state whether the owner’s number is contractual, indicative or remeasurable.
Should provisional work be ordered before the quantity is confirmed?
Follow the signed contract and site procedure. As a control principle, confirm the safe survey, issue the authorized instruction and agree the valuation basis before committing material or labour where practicable.
Does a final measured quantity prove the installation is accepted?
No. Measurement supports valuation. Technical acceptance still requires the specified inspection, verification, functional tests, documentation and closure of nonconformities.
Owner checklist before tender release
- Each provisional line has one clear physical uncertainty.
- The BOQ distinguishes route-metres, conductor-metres, points, each and sets.
- Drawings and information revisions are listed.
- Rate inclusions and exclusions are explicit.
- The release survey, owner and deadline are named.
- Joint measurement and evidence formats are attached.
- Instruction and valuation authority matches the draft contract.
- HSE, testing and documentation are not hidden as optional quantities.
- Bid comparison removes duplicate allowances and qualifications.
- Final quantities reconcile to as-built and acceptance records.
Conclusion
A useful provisional quantity turns a known information gap into a controlled procurement decision. Define the item, unit, boundary, evidence, release event and valuation rule before bids are compared. Then reconcile the installed quantity without confusing measurement with technical acceptance.
For a factory-specific tender review, prepare the latest single-line diagram, equipment schedule, route drawings, room layouts, vendor-interface register, shutdown constraints and draft BOQ. QuangAnhcons can structure an owner-side electrical quantity-basis and clarification matrix from that information; final design, contract terms and regulatory obligations remain project-specific.
Primary references
- World Bank Project Procurement Framework — official source for Standard Procurement Documents and procurement guidance; project applicability is separate.
- IEC 60364-6:2016 — official catalogue scope for initial and periodic verification of LV installations.
- IEC 61439-2:2020 — official catalogue scope for power switchgear and controlgear assemblies.
- IEC 62271-200:2021 and Amendment 1:2024 — official catalogue scope for AC metal-enclosed switchgear.


Related Posts
Provisional Quantities in Factory Electrical Tenders: Define the Rule Before Pricing
Define provisional electrical quantities with measurable units, release triggers, unit-rate inclusions, joint records and a [...]
Electrical Thermography Reports: What a Factory Owner Must Receive
Define a useful electrical thermography report for a Vietnam factory: asset identity, operating load, camera [...]
Backup Power Acceptance Tests: A Production-Safe Factory Plan
Plan generator and ATS acceptance around production constraints, with a controlled test sequence, P/Q load [...]
EV Charging Load Management: Requirements for a Corporate Fleet RFQ
Define site power caps, fleet priorities, offline behaviour, data, BOQ and scenario-based acceptance tests for [...]
BESS Supplier Safety Documentation: An Owner’s RFQ and Acceptance Register
A configuration-specific BESS safety-document register for RFQ, design review, FAT, SAT, change control and owner [...]
Factory Rooftop Solar Installation: Plan the Work Around Production, Not Across It
Build a rooftop PV installation plan around factory production, with roof zones, permits, lifting, isolation [...]
Factory Electrical Spare Capacity: Define What 20% Means Before Tender Award
Turn a vague 20% electrical spare-capacity promise into measurable demand, thermal, fault-duty, physical-space and expansion-interface [...]
Manufacturer Certificates vs Site Test Evidence: What an FDI Owner Should Accept
Separate manufacturer certificates, factory test records and site commissioning evidence with a traceable acceptance matrix [...]
Electrical Equipment Storage Before Installation: A Release Matrix for Vietnam Factory Projects
Define storage, preservation and release controls for MV/LV switchgear, transformers, cables and auxiliaries before electrical [...]
Design Freeze Milestones for Factory Electrical Procurement: What Must Be Fixed Before Release
Freeze the right electrical design inputs before factory procurement: ratings, MV/LV interfaces, vendor documents, hold [...]
Rooftop PV Export-Limit Commissioning: Prove the Control at the Grid Meter
Commission a rooftop PV export-limit scheme at the point of connection with CT checks, load-drop [...]
BESS Auxiliary Load and Temperature Derating: A Site Acceptance Test for Net Performance
Test BESS net AC energy, standby auxiliaries, HVAC demand and temperature derating with explicit meter [...]
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]