A fleet depot rarely needs every charger on day one, but it does need an electrical backbone that can expand without repeated excavation, unplanned shutdowns or stranded switchboard capacity. The procurement question is which bays are reserved, civil-ready, power-ready and commissioned in each phase, and what evidence proves each state.
This Vietnam-oriented guide gives FDI owners, logistics operators and EPC teams a method for packaging a phased EV depot. The example is hypothetical and supports screening only; it does not replace the project load study, protection study, utility agreement or authority review.
1. Define four bay states
- Reserved: space is protected, with no claim about ducts, cables or available capacity.
- Civil-ready: foundations, sleeves, drainage protection, bollards and draw pits are complete; electrical capacity is not released.
- Power-ready: a stated charger rating has a documented feeder route, containment allowance, protective-device position, earthing provision and upstream capacity allocation. The BOQ must state whether the final cable is installed.
- Commissioned: charger, feeder, protection, controls and communications have passed the project acceptance tests.
“Future charger” is too vague: it can mean an empty bay, a capped duct or a protected spare way. The four states create measurable deliverables.
2. Build phases from fleet duty data
Record vehicle count, usable battery energy, arrival and required departure state of charge, dwell duration, simultaneous dispatch constraints and seasonal cases. See our guides to EV fleet sizing from operational data and the industrial EV depot design brief.
| Phase | Scope | Bay state at handover | Decision |
|---|---|---|---|
| 1 | 12 vehicles, overnight | 12 commissioned + 8 power-ready | Release initial controlled demand |
| 2 | 40 vehicles, mixed shifts | 28 more commissioned | Revalidate transformer and feeder headroom |
| 3 | Growth or faster turnaround | Upgrade remaining bays | Study network upgrade or storage alternative |
3. Screen energy and demand
Daily AC energy = vehicles × DC energy per vehicle ÷ charging efficiency + auxiliary energy.
For Phase 1, assume 12 vehicles require 28 kWh DC each, charging efficiency is 90%, auxiliaries draw 2 kW, and the window is eight hours:
- DC energy = 12 × 28 = 336 kWh.
- AC charging energy = 336 ÷ 0.90 = 373.33 kWh.
- Auxiliary energy = 2 × 8 = 16 kWh.
- Average input = (373.33 + 16) ÷ 8 = 48.67 kW.
For Phase 2 with 40 vehicles and a ten-hour window:
- AC charging energy = (40 × 28) ÷ 0.90 = 1,244.44 kWh.
- Total AC energy = 1,244.44 + 20 = 1,264.44 kWh.
- Average input = 1,264.44 ÷ 10 = 126.44 kW.
A 150 kW management cap leaves a simple average-power margin of 23.56 kW. That is not proof of compliance: arrival clustering, charger minimum power, factory peaks, harmonics and contingency behaviour require time-series and network checks.
At 400 V three-phase and power factor 0.99, the screening current at 150 kW is I = 150,000 ÷ (√3 × 400 × 0.99) = 218.7 A. Final conductor and protection selection must apply installation method, ambient temperature, grouping, soil thermal conditions, voltage drop, fault current and OEM requirements.
4. Freeze the common backbone
- SLD and normal/emergency supply boundary;
- transformer and MSB demand allocation;
- spare ways, busbar rating and short-circuit withstand;
- feeder routes, containment fill and draw-pit geometry;
- earthing, bonding and surge-protection concept;
- communications topology, time source and cybersecurity ownership;
- metering boundary and data-retention requirements;
- fire strategy, traffic, impact protection and drainage interfaces;
- load-management states and loss-of-communications behaviour.
Reserve space and routes independently from electrical capacity. Drawings may show twenty future bays while the approved demand envelope initially releases only eight.
5. Make “power-ready” auditable
For each power-ready bay, identify the charger design rating, upstream panel and spare way, protective-device envelope, feeder route and assumed length, containment reserve, earthing point, communications termination and the study revision supporting the allocation.
Mark exclusions explicitly: “final feeder excluded; draw rope and capped conduit included” or “MCCB installed and locked open; downstream cable excluded.” This prevents a power-ready claim being mistaken for an energised circuit.
6. Separate charger and site controls
The charger management system should receive an import limit or available-power signal and allocate power among chargers. Define update interval, stale-data timeout, restart behaviour, local fallback limit and alarm path. State whether the cap is enforced by charger management, site energy management or both.
If OCPP is specified, identify the required functions and test them. A protocol label alone does not prove smart charging, offline behaviour or backend interoperability. ISO 15118 functions depend on vehicle, charger, certificate and backend support. Treat Plug & Charge or bidirectional operation as scoped options with an interface matrix and acceptance script.
7. Protect factory production
- Normal: chargers share the approved cap.
- Factory peak: charging is reduced to protect the site import or transformer limit.
- Communications loss: each charger falls to a documented local limit or stops according to the risk review.
- Emergency or islanded: availability follows the approved essential-load philosophy.
Test transitions. A steady dashboard screenshot does not demonstrate safe behaviour after meter loss, controller restart or network outage.
8. Re-run studies at each gate
Before moving bays from reserved or civil-ready to power-ready, update the load schedule and confirm upstream capacity. Before commissioning, confirm OEM data and refresh voltage-drop, short-circuit, protection-coordination, earthing and harmonic assessments.
The specification should name adopted editions, including applicable installation requirements and IEC 60364-7-722 for EV supplies. Charger requirements should map to the applicable IEC 61851 series and exact OEM documents. Vietnam compliance depends on project scope, current QCVN/TCVN requirements, utility conditions and authority decisions; a generic standards list is not an approval basis.
9. Split the BOQ
| Package | Typical inclusions | Quantity basis |
|---|---|---|
| Common backbone | Panel extension, metering, controller, network core, common containment | One lot with ratings |
| Civil-ready bay | Foundation, sleeves, draw pit, drainage, bollards | Per bay and route metre |
| Power-ready bay | Spare way, protection provision, earthing point, labelled route | Per bay with charger rating |
| Commissioned charger | Charger, final feeder, isolation, data, configuration, tests | Per model and connector count |
| Studies/integration | Network studies, logic, backend setup, scripts | Per phase/revision |
| Training/spares | Training, spares, licences, handover data | Schedule with renewal terms |
Require exclusions and later-conversion unit rates so the owner receives a comparable Phase 1 price and visible expansion basis.
10. Hold points
- HP-01: fleet data, phase matrix and capacity envelope approved.
- HP-02: surveyed routes, drainage, fire access and structural interfaces approved before excavation.
- HP-03: OEM data, fault rating, protection and communications accepted before purchase.
- HP-04: sleeves, ducts, earthing and pits inspected before backfill.
- HP-05: test records, settings, labels and as-builts accepted before energisation.
- HP-06: load management, alarms, transactions and failure modes demonstrated.
11. Test as a system
The ITP should cover document review, equipment identity, visual inspection, continuity, insulation, earthing, phase sequence, protection settings, functional tests and metering. Use realistic simultaneous sessions to test cap enforcement, departure priority, loss of site meter, loss of backend communications, controller restart, alarms and power-interruption recovery.
Record calibrated instruments, conditions, firmware, configuration exports, timestamps, criteria, witnesses and corrective-action closure. Handover should include as-built SLDs, cable schedules, settings, asset IDs, network addressing, account ownership, licence terms, backups, training and the phase-conversion register.
Owner release checklist
- Are the four bay states defined per bay?
- Does every phase have dated fleet-energy assumptions?
- Is the cap coordinated with factory demand?
- Are spare ways, routes and containment traceable?
- Does the BOQ identify excluded final feeders?
- Are protocol features tied to test cases?
- Will studies be refreshed with final OEM data?
- Are loss-of-comms and emergency states accepted?
- Are future unit rates and responsibilities visible?
Frequently asked questions
Does a capped duct make a bay power-ready?
No. It is normally civil-ready unless upstream capacity, protection position, earthing provision, route assumptions and design rating are documented and accepted.
Should final feeder cables be installed in Phase 1?
Decide after comparing ageing, damage risk, route access, future charger ratings and shutdown cost. State the boundary in the BOQ.
Can charger nameplate power be added directly to factory peak?
It is a conservative starting point. A verified management cap can reduce coincident demand, but the architecture and failure behaviour belong in the study.
Is average power enough to size the connection?
No. It checks energy feasibility. Time-step demand, simultaneity, upstream peaks, losses, harmonics, voltage drop and contingencies determine design.
When should Phase 2 equipment be ordered?
After the fleet forecast, capacity study, OEM data, interface matrix and cost comparison pass the release gate.
Prepare a priceable phase package
Quang Anh can help FDI owners and EPC teams convert fleet duty data into a phased design basis, SLD, capacity screen, BOQ split, responsibility matrix and commissioning plan for Vietnam projects. Send route groups, dwell windows, transformer/MSB data and expansion dates to define the RFQ package.
Source register
- IEC 60364-7-722:2018: official page.
- IEC 61851-1:2017: official page.
- Open Charge Alliance, OCPP: official page.
- ISO 15118-20:2022: official page.
- U.S. DOE AFDC electric fleets: official page.
- NREL EVI-LOCATE: official tool.
Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]
Energy-Savings Proposals: Compare Baselines Before Comparing Percent Savings
Compare factory energy-saving proposals on one auditable baseline: align boundaries, production adjustments, reporting periods, meter [...]
Fleet Operating Data Before EV Charging-Site Sizing: An Owner’s Input Pack
Build a defensible fleet-charging input pack from routes, arrival and departure times, energy, vehicle acceptance, [...]
BESS Duty-Cycle Assumptions: An Owner’s Audit for Vietnam Factories
Audit BESS duty-cycle assumptions for a Vietnam factory: services, SOC reserve, power-duration, efficiency, throughput, degradation, [...]
Rooftop Solar Investment Assumptions: A Finance-Team Challenge List for Vietnam Factories
Audit rooftop-solar investment assumptions for a Vietnam factory: load matching, yield, losses, availability, degradation, cash-flow [...]
Material Traceability for Factory Electrical Packages: Records an FDI Owner Can Audit
Define auditable material traceability for factory electrical packages: serial and batch links, receipt and quarantine, [...]
Electrical EPC Training Deliverables: An Owner’s Contract Guide
Define electrical EPC training by role, task, revision, safety boundary and acceptance evidence. Includes an [...]
Electrical Single Points of Failure: Rank the Production Consequence
Build a factory electrical consequence register around functions, shared dependencies and credible recovery paths. Compare [...]
Shared BESS for Factory Tenants: Separate Control from Energy Allocation
Define shared BESS electrical, command and tenant allocation boundaries before procurement, with a checked common-meter [...]
Electrical Handover Dossier: Make It Usable for an Overseas Facility Team
Specify an electrical handover dossier that an overseas facility team can actually use: asset links, [...]
Switchboard FAT Report Review: Evidence Before Dispatch
Review the switchboard FAT evidence chain before dispatch: assembly identity, drawing revisions, verification records, actual [...]
Factory Substation Delivery: Prove the Access Route Before Dispatch
Build a route evidence pack before dispatching factory electrical equipment: shipping envelopes, access constraints, receiving [...]
Owner-Supplied Electrical Equipment: Custody and Acceptance for a Vietnam Factory
Agree receipt, custody, preservation, technical release and operational acceptance when a factory owner buys electrical [...]
Factory Electrical Metering Boundaries: An Energy Reporting Brief
Define factory electrical metering boundaries before comparing energy performance: separate grid exchange, generation, battery flows, [...]
Oct
Electrical Maintenance Tender Scope for an FDI Factory: Assets, Access and Evidence
Prepare a comparable electrical maintenance tender for an FDI factory: asset scope, outage interfaces, workload [...]
Oct
Industrial BESS Owner Requirements in Vietnam: A Procurement Brief Bidders Can Price
Define an industrial BESS owner requirement for a Vietnam factory: AC boundary, duty, safety, interfaces, [...]
Oct