22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size

A cable schedule that says “22 kV, 3 × 1C × 240 mm²” is not an ampacity study. The acceptable size depends on the route: soil temperature and thermal resistivity, burial depth, ducts, grouping, screen bonding, adjacent heat sources, load factor and the conductor temperature agreed with the cable manufacturer.

This guide gives FDI owners and EPC teams a route-data pack for a factory feeder in Vietnam. The numerical example is a screening case, not a design approval. Final selection must use surveyed conditions, utility requirements, the current project-adopted QCVN/TCVN, the exact cable datasheet and the approved study method.

1. Freeze the electrical duty

Record normal, contingency, starting and future currents separately. For a three-phase apparent-power case:

I = S /(√3 × U).

At 22 kV, 10 MVA gives 10,000/(√3 × 22) = 262.4 A. A 12.5 MVA contingency gives 328.0 A. If the owner applies a 15% planning margin to that defined case, the screening target is 328.0 × 1.15 = 377.2 A. The margin must not hide an undefined expansion load.

State duration and coincidence. A transformer emergency rating, a motor-start transient and a continuous process load do not use the same thermal assumption.

2. Divide the route into thermal sections

Section Required input Typical risk
Substation trench Tray arrangement, ventilation, other circuits Grouping and hot enclosure
Duct bank Duct material, spacing, concrete, occupancy High external thermal resistance
Direct buried Depth, soil/backfill resistivity, moisture Seasonal drying
Road crossing Sleeve length, spare ducts, cover Local thermal bottleneck
Riser/termination Sun, enclosure, bend radius, cleats Mechanical and ambient limits

Calculate each section and let the limiting credible section govern. Do not average a short congested duct bank with a long favourable buried route.

3. Issue an input register

  • cable construction, conductor material, insulation, screen and armour;
  • maximum conductor temperature agreed for normal and short-circuit duties;
  • ambient air and soil temperatures with basis and season;
  • soil and selected-backfill thermal resistivity, including dry-out case;
  • burial depth, duct geometry, spacing and concrete envelope;
  • number of loaded circuits, phase arrangement and load factor;
  • screen bonding and earthing arrangement;
  • harmonic content where it can change conductor or screen losses;
  • route length, joint positions and adjacent heat sources;
  • installation tolerances and future occupied ducts.

IEC 60287-1-1:2023 covers steady-state current-rating equations and losses and deliberately leaves several site and user-agreed parameters to the project. That is why a software output without an input register is not reviewable.

4. Model screen bonding explicitly

Single-core MV cable screens can create circulating and eddy-current losses. Record single-point, both-end or cross-bonded arrangements, link-box locations, sheath-voltage limiters and earth continuity. The bonding design affects ampacity, induced voltage, fault-current path, testing and the BOQ.

For long feeders, segment lengths and phase transposition matter. Ask the bidder to provide the calculation model and the installation drawing from the same revision.

5. Check more than ampacity

  • Voltage: calculate normal and starting voltage drop using the selected conductor and actual power factor.
  • Short circuit: verify conductor and metallic screen thermal withstand for the protection clearing time.
  • Protection: confirm earth-fault sensitivity, CT range and coordination.
  • Mechanical: confirm pulling tension, sidewall pressure, bend radius, cleat spacing and fault-force restraint.
  • Terminations: match conductor, insulation system, equipment interface and environmental class.

IEC 60502-2:2014+AMD1:2024 CSV, including Corrigendum 1:2026 in the current consolidated copy, addresses construction and tests for extruded MV cables. It does not replace the route-specific rating calculation.

6. Compare options on the same basis

Bid field Required response
Rated duty Normal, contingency and future current with duration
Installation Section-by-section route geometry and thermal inputs
Result Rating, conductor temperature and limiting section
Losses Conductor, screen and dielectric losses at stated load
Bonding Diagram, link boxes, SVLs and earth connections
Accessories Manufacturer, type tests, interfaces and quantities
Construction Pulling plan, joint bays, testing and reinstatement

7. BOQ and method-statement boundaries

Separate cable route metres from procurement metres. Include drum schedule and allowances transparently. List cable, terminations, joints, link boxes, SVLs, earth conductors, cleats, markers, ducts, selected backfill, warning tape, route posts, fire stopping and test work as identifiable items.

The method statement should cover survey release, drum inspection, trench/duct acceptance, pulling calculation, pulling records, bend control, phase identification, jointing cleanliness, screen bonding, earthing, test sequence and as-built coordinates.

8. ITP hold points

  • HP-01: route survey and thermal input register accepted.
  • HP-02: study and manufacturer data accepted before purchase.
  • HP-03: trench, ducts, spacers and backfill batch accepted before laying.
  • HP-04: pulling plan and calibrated equipment accepted before pull.
  • HP-05: jointing personnel, environment and kits verified.
  • HP-06: bonding, earthing, tests and as-builts accepted before energisation.

Owner checklist

  • Is every thermal section represented?
  • Are soil inputs measured or explicitly conservative?
  • Are spare ducts assumed occupied in the future case?
  • Does screen bonding match the loss model?
  • Are ampacity, voltage drop and short circuit all passed?
  • Can the BOQ be reconciled to route and drum schedules?
  • Are test criteria tied to the adopted cable and accessory documents?

Frequently asked questions

Can a manufacturer ampacity table select the feeder?

Only when its installation assumptions match every governing route section. Usually they do not, so document the deviations and calculate the project case.

Is the largest cross-section always safest?

No. Larger cable changes bending, pulling, terminations, cost and screen behaviour. Select the smallest compliant option with stated margin and constructability.

Should measured soil resistivity be one number?

Use locations, depths and seasonal interpretation appropriate to the route. Include the selected backfill and dry-out assumptions.

Can two circuits in one bank keep their individual table ratings?

Not without a grouping model. Mutual heating and occupancy must be included.

Prepare the feeder package

Quang Anh can help owners and EPC teams convert a surveyed 22 kV route into a calculation input register, option matrix, cable schedule, BOQ, method statement and ITP. Share the SLD, duty cases, route sections, geotechnical data and utility interface for a priceable review.

Source register

[contact-form-7 id="7239967" title="Contact form 1"]

Quick substation quotation

Loading the tool…

Developed and operated by QuangAnhcons. Results are preliminary estimates based on the information provided; the configuration, scope and price are confirmed in the quotation or contract before ordering or construction.

Quick Substation 2.1.16-rc1

© 2026 QUANG ANH CE CO., LTD. Please retain the issuer’s name and reference when saving or sharing documents. Third-party names, trademarks and materials belong to their respective owners.

Related Posts