A cable schedule that says “22 kV, 3 × 1C × 240 mm²” is not an ampacity study. The acceptable size depends on the route: soil temperature and thermal resistivity, burial depth, ducts, grouping, screen bonding, adjacent heat sources, load factor and the conductor temperature agreed with the cable manufacturer.
This guide gives FDI owners and EPC teams a route-data pack for a factory feeder in Vietnam. The numerical example is a screening case, not a design approval. Final selection must use surveyed conditions, utility requirements, the current project-adopted QCVN/TCVN, the exact cable datasheet and the approved study method.
1. Freeze the electrical duty
Record normal, contingency, starting and future currents separately. For a three-phase apparent-power case:
I = S /(√3 × U).
At 22 kV, 10 MVA gives 10,000/(√3 × 22) = 262.4 A. A 12.5 MVA contingency gives 328.0 A. If the owner applies a 15% planning margin to that defined case, the screening target is 328.0 × 1.15 = 377.2 A. The margin must not hide an undefined expansion load.
State duration and coincidence. A transformer emergency rating, a motor-start transient and a continuous process load do not use the same thermal assumption.
2. Divide the route into thermal sections
| Section | Required input | Typical risk |
|---|---|---|
| Substation trench | Tray arrangement, ventilation, other circuits | Grouping and hot enclosure |
| Duct bank | Duct material, spacing, concrete, occupancy | High external thermal resistance |
| Direct buried | Depth, soil/backfill resistivity, moisture | Seasonal drying |
| Road crossing | Sleeve length, spare ducts, cover | Local thermal bottleneck |
| Riser/termination | Sun, enclosure, bend radius, cleats | Mechanical and ambient limits |
Calculate each section and let the limiting credible section govern. Do not average a short congested duct bank with a long favourable buried route.
3. Issue an input register
- cable construction, conductor material, insulation, screen and armour;
- maximum conductor temperature agreed for normal and short-circuit duties;
- ambient air and soil temperatures with basis and season;
- soil and selected-backfill thermal resistivity, including dry-out case;
- burial depth, duct geometry, spacing and concrete envelope;
- number of loaded circuits, phase arrangement and load factor;
- screen bonding and earthing arrangement;
- harmonic content where it can change conductor or screen losses;
- route length, joint positions and adjacent heat sources;
- installation tolerances and future occupied ducts.
IEC 60287-1-1:2023 covers steady-state current-rating equations and losses and deliberately leaves several site and user-agreed parameters to the project. That is why a software output without an input register is not reviewable.
4. Model screen bonding explicitly
Single-core MV cable screens can create circulating and eddy-current losses. Record single-point, both-end or cross-bonded arrangements, link-box locations, sheath-voltage limiters and earth continuity. The bonding design affects ampacity, induced voltage, fault-current path, testing and the BOQ.
For long feeders, segment lengths and phase transposition matter. Ask the bidder to provide the calculation model and the installation drawing from the same revision.
5. Check more than ampacity
- Voltage: calculate normal and starting voltage drop using the selected conductor and actual power factor.
- Short circuit: verify conductor and metallic screen thermal withstand for the protection clearing time.
- Protection: confirm earth-fault sensitivity, CT range and coordination.
- Mechanical: confirm pulling tension, sidewall pressure, bend radius, cleat spacing and fault-force restraint.
- Terminations: match conductor, insulation system, equipment interface and environmental class.
IEC 60502-2:2014+AMD1:2024 CSV, including Corrigendum 1:2026 in the current consolidated copy, addresses construction and tests for extruded MV cables. It does not replace the route-specific rating calculation.
6. Compare options on the same basis
| Bid field | Required response |
|---|---|
| Rated duty | Normal, contingency and future current with duration |
| Installation | Section-by-section route geometry and thermal inputs |
| Result | Rating, conductor temperature and limiting section |
| Losses | Conductor, screen and dielectric losses at stated load |
| Bonding | Diagram, link boxes, SVLs and earth connections |
| Accessories | Manufacturer, type tests, interfaces and quantities |
| Construction | Pulling plan, joint bays, testing and reinstatement |
7. BOQ and method-statement boundaries
Separate cable route metres from procurement metres. Include drum schedule and allowances transparently. List cable, terminations, joints, link boxes, SVLs, earth conductors, cleats, markers, ducts, selected backfill, warning tape, route posts, fire stopping and test work as identifiable items.
The method statement should cover survey release, drum inspection, trench/duct acceptance, pulling calculation, pulling records, bend control, phase identification, jointing cleanliness, screen bonding, earthing, test sequence and as-built coordinates.
8. ITP hold points
- HP-01: route survey and thermal input register accepted.
- HP-02: study and manufacturer data accepted before purchase.
- HP-03: trench, ducts, spacers and backfill batch accepted before laying.
- HP-04: pulling plan and calibrated equipment accepted before pull.
- HP-05: jointing personnel, environment and kits verified.
- HP-06: bonding, earthing, tests and as-builts accepted before energisation.
Owner checklist
- Is every thermal section represented?
- Are soil inputs measured or explicitly conservative?
- Are spare ducts assumed occupied in the future case?
- Does screen bonding match the loss model?
- Are ampacity, voltage drop and short circuit all passed?
- Can the BOQ be reconciled to route and drum schedules?
- Are test criteria tied to the adopted cable and accessory documents?
Frequently asked questions
Can a manufacturer ampacity table select the feeder?
Only when its installation assumptions match every governing route section. Usually they do not, so document the deviations and calculate the project case.
Is the largest cross-section always safest?
No. Larger cable changes bending, pulling, terminations, cost and screen behaviour. Select the smallest compliant option with stated margin and constructability.
Should measured soil resistivity be one number?
Use locations, depths and seasonal interpretation appropriate to the route. Include the selected backfill and dry-out assumptions.
Can two circuits in one bank keep their individual table ratings?
Not without a grouping model. Mutual heating and occupancy must be included.
Prepare the feeder package
Quang Anh can help owners and EPC teams convert a surveyed 22 kV route into a calculation input register, option matrix, cable schedule, BOQ, method statement and ITP. Share the SLD, duty cases, route sections, geotechnical data and utility interface for a priceable review.
Source register
- IEC 60287-1-1:2023: official IEC page.
- IEC 60502-2:2014+AMD1:2024 CSV/COR1:2026: official IEC page.
Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]
Energy-Savings Proposals: Compare Baselines Before Comparing Percent Savings
Compare factory energy-saving proposals on one auditable baseline: align boundaries, production adjustments, reporting periods, meter [...]
Fleet Operating Data Before EV Charging-Site Sizing: An Owner’s Input Pack
Build a defensible fleet-charging input pack from routes, arrival and departure times, energy, vehicle acceptance, [...]
BESS Duty-Cycle Assumptions: An Owner’s Audit for Vietnam Factories
Audit BESS duty-cycle assumptions for a Vietnam factory: services, SOC reserve, power-duration, efficiency, throughput, degradation, [...]
Rooftop Solar Investment Assumptions: A Finance-Team Challenge List for Vietnam Factories
Audit rooftop-solar investment assumptions for a Vietnam factory: load matching, yield, losses, availability, degradation, cash-flow [...]
Material Traceability for Factory Electrical Packages: Records an FDI Owner Can Audit
Define auditable material traceability for factory electrical packages: serial and batch links, receipt and quarantine, [...]
Electrical EPC Training Deliverables: An Owner’s Contract Guide
Define electrical EPC training by role, task, revision, safety boundary and acceptance evidence. Includes an [...]
Electrical Single Points of Failure: Rank the Production Consequence
Build a factory electrical consequence register around functions, shared dependencies and credible recovery paths. Compare [...]
Shared BESS for Factory Tenants: Separate Control from Energy Allocation
Define shared BESS electrical, command and tenant allocation boundaries before procurement, with a checked common-meter [...]
Electrical Handover Dossier: Make It Usable for an Overseas Facility Team
Specify an electrical handover dossier that an overseas facility team can actually use: asset links, [...]
Switchboard FAT Report Review: Evidence Before Dispatch
Review the switchboard FAT evidence chain before dispatch: assembly identity, drawing revisions, verification records, actual [...]
Factory Substation Delivery: Prove the Access Route Before Dispatch
Build a route evidence pack before dispatching factory electrical equipment: shipping envelopes, access constraints, receiving [...]
Owner-Supplied Electrical Equipment: Custody and Acceptance for a Vietnam Factory
Agree receipt, custody, preservation, technical release and operational acceptance when a factory owner buys electrical [...]