“Smart charging included” is not a load-management specification. A corporate fleet owner needs an enforceable site power limit, a prioritisation policy, offline behaviour, data ownership, test scenarios and clear boundaries between chargers, the charging-management system, meters, network and building electrical system.
This guide turns fleet duty and site constraints into an RFQ and acceptance package for a Vietnam facility. It does not select a tariff, guarantee vehicle availability, approve a grid connection or certify protocol interoperability.
1. Start with three controlled inputs
First, define the site import limit and how it is measured. Second, provide time-series non-EV demand or a conservative envelope. Third, convert each vehicle route into arrival time, departure deadline, energy required, minimum reserve and operational priority. Name the source, sampling interval, missing-data rule and owner of each input.
Do not size from the sum of charger nameplates. The system must allocate limited power to meet departures while respecting the electrical ceiling and equipment limits.
2. Calculate the dynamic EV ceiling
For an illustrative interval, assume a firm site import ceiling of 800 kW, measured non-EV demand of 520 kW and an owner reserve of 80 kW. The permitted EV power is:
P_EV,limit = 800 - 520 - 80 = 200 kW.
Assume twelve vans each require 80 kWh delivered to the battery and the planning efficiency from grid meter to stored energy is 92%. Grid energy required is 12 × 80 / 0.92 = 1,043 kWh. Over an eight-hour window the average is about 130 kW; over six hours it is about 174 kW. Both averages are below 200 kW, but feasibility still depends on arrival times, charger/vehicle limits, tapering, downtime and the priority policy. The calculation is a screening check, not a dispatch guarantee.
3. Specify the control hierarchy
| Layer | Required rule | Failure behaviour to test |
|---|---|---|
| Site controller | Enforce the measured import ceiling and reserve | Meter stale, meter reversed, controller reboot |
| CSMS | Allocate energy by departure, priority and state | Cloud link lost, command delayed, database unavailable |
| Charger | Respect commanded current/power within rated limits | Command timeout, local restart, connector fault |
| Vehicle | Report or infer charging limits and session status | No state-of-charge data, vehicle rejects setpoint |
| Operator | Use authorised override with audit trail and expiry | Conflicting override or expired priority |
The RFQ should state whether the power limit is hard, what measurement delay is permitted, how reserve is applied, the ramp rate, minimum charger allocation, fairness rule, departure priority, emergency override and restoration after a fault. It should also define whether a local controller can maintain the cap when the cloud service is unavailable.
4. Separate protocol claims from delivered functions
IEC 63110-1:2022 defines an architecture and use cases for managing EV charging infrastructure, including energy transfer, assets and cybersecurity. IEC 61851-23:2023 covers DC EV supply equipment; IEC 61851-24:2023 covers digital communication between DC EVSE and an EV for charging control. Vietnam’s active TCVN 13078-1:2020 and TCVN 13078-23:2020 provide national references corresponding to conductive charging system requirements. Confirm the editions and applicability in the approved design.
OCPP support is not enough. State the required OCPP edition, security profile, smart-charging functions, transaction recovery, certificate management, data fields and test cases. The Open Charge Alliance describes smart charging through charging profiles, but certification profiles and product implementations differ. Require evidence for the exact charger and software release offered.
5. Define data, cybersecurity and service boundaries
- Owner of charger, session, meter, vehicle and user data; retention and export format.
- Network segmentation, authentication, certificate lifecycle, remote-access approval and event logging.
- Time synchronisation, timezone, daylight-saving treatment, missing samples and corrected records.
- Software/firmware inventory, vulnerability notification, supported versions and rollback.
- Local safe state and continued power-cap enforcement during WAN, CSMS or meter failure.
- Support hours, incident severity, response, restoration, root-cause report and configuration backup.
Keep personal data and fleet-operational data minimised. The technical schedule should identify who can see vehicle identity, driver identity, location and charging history, and how access is removed.
6. Write FAT and SAT around scenarios
- Design hold: SLD, meter architecture, maximum-demand basis, control hierarchy, network and data map approved.
- FAT: simulate site-load changes, priorities, departure deadlines, charger unavailability, stale meter data and loss of communications.
- Installation hold: protective devices, cable ratings, metering polarity/ratios, earthing, labels, network separation and emergency controls inspected.
- SAT cap test: step non-EV load upward and verify aggregate EV demand reduces without exceeding the agreed time and tolerance.
- SAT recovery: reboot charger, controller and communications in controlled scenarios; confirm sessions, limits and audit records recover as specified.
- Operational trial: run representative vehicles and departure priorities; reconcile meter energy, CSMS records and vehicle outcomes.
Acceptance criteria must state sampling interval, tolerance, duration and evidence. “No overload observed” is not a reproducible result. Record source meter values, controller limit, charger commands, actual charger power, timestamps, alarms and operator actions.
7. Clarify the BOQ
Separate chargers, pedestals, cable and containment, switchboard feeders, protection, meters, site controller, CSMS licences, SIM/network, cybersecurity services, commissioning, training, software support and data export. Name responsibility for utility capacity, transformer/MSB studies, civil works, line marking, barriers, drainage, fire strategy and vehicle compatibility.
Coordinate the RFQ with the fleet operating-data sizing method, corporate charging procurement brief, phased rollout and power-cap plan and electrical metering boundaries.
Owner action
Issue one scenario-based compliance matrix to every bidder and require an exception for every unproven function. QuangAnhcons can develop the load envelope, SLD interfaces, BOQ and witnessed acceptance scripts through the industrial project enquiry.
Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
EV Charging Load Management: Requirements for a Corporate Fleet RFQ
Define site power caps, fleet priorities, offline behaviour, data, BOQ and scenario-based acceptance tests for [...]
BESS Supplier Safety Documentation: An Owner’s RFQ and Acceptance Register
A configuration-specific BESS safety-document register for RFQ, design review, FAT, SAT, change control and owner [...]
Factory Rooftop Solar Installation: Plan the Work Around Production, Not Across It
Build a rooftop PV installation plan around factory production, with roof zones, permits, lifting, isolation [...]
Factory Electrical Spare Capacity: Define What 20% Means Before Tender Award
Turn a vague 20% electrical spare-capacity promise into measurable demand, thermal, fault-duty, physical-space and expansion-interface [...]
Manufacturer Certificates vs Site Test Evidence: What an FDI Owner Should Accept
Separate manufacturer certificates, factory test records and site commissioning evidence with a traceable acceptance matrix [...]
Electrical Equipment Storage Before Installation: A Release Matrix for Vietnam Factory Projects
Define storage, preservation and release controls for MV/LV switchgear, transformers, cables and auxiliaries before electrical [...]
Design Freeze Milestones for Factory Electrical Procurement: What Must Be Fixed Before Release
Freeze the right electrical design inputs before factory procurement: ratings, MV/LV interfaces, vendor documents, hold [...]
Rooftop PV Export-Limit Commissioning: Prove the Control at the Grid Meter
Commission a rooftop PV export-limit scheme at the point of connection with CT checks, load-drop [...]
BESS Auxiliary Load and Temperature Derating: A Site Acceptance Test for Net Performance
Test BESS net AC energy, standby auxiliaries, HVAC demand and temperature derating with explicit meter [...]
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]
Energy-Savings Proposals: Compare Baselines Before Comparing Percent Savings
Compare factory energy-saving proposals on one auditable baseline: align boundaries, production adjustments, reporting periods, meter [...]
Fleet Operating Data Before EV Charging-Site Sizing: An Owner’s Input Pack
Build a defensible fleet-charging input pack from routes, arrival and departure times, energy, vehicle acceptance, [...]