A generator starting with no load does not prove that a factory will restore safely. The acceptance test must demonstrate the complete chain: source-loss detection, start command, voltage and frequency readiness, transfer, staged loading, alarms, failed conditions, return transfer and cooldown.
This guide gives owners and EPC teams a test structure for Vietnam factory projects. Example settings and loads are hypothetical. The approved design, generator and ATS manufacturer limits, life-safety strategy, utility conditions and current QCVN/TCVN govern the real test.
1. Define the test boundary
Mark on the SLD the normal source, generator, ATS/TSE, emergency or essential bus, load-shedding devices, UPS/BESS interfaces and downstream panels. State whether the test begins at a simulated voltage input, an opened normal-source breaker or an actual upstream outage.
List excluded loads and temporary operating restrictions. A safe simulated input test and a full integrated power test provide different evidence.
2. Build a sequence-of-events table
| Milestone | Evidence |
|---|---|
| Normal source unacceptable | Measured voltage/frequency and controller timestamp |
| Start command | ATS output and generator input |
| Generator ready | Voltage, frequency, ready contact |
| Normal source opened | Command and auxiliary contact |
| Emergency source closed | Command, position and bus voltage |
| Load stages added | kW, kvar, current, voltage, frequency |
| Normal source stable | Return timer start and completion |
| Cooldown/stop | Unload, timer and stop state |
Use one synchronized time source or record offsets. Controller screenshots alone cannot correlate breaker, generator and power-quality events.
3. Establish the restoration envelope
Example only: source detection delay 2.0 s, generator ready in 10.0 s after start, and transfer 1.5 s after readiness. The electrical restoration is 2.0 + 10.0 + 1.5 = 13.5 s. Compare that result with each load’s permitted interruption.
Keep safety-service requirements separate from production-continuity targets. IEC 60364-5-56:2018 addresses supplies for safety services; the project must state its adopted requirements and authority interfaces.
4. Test realistic load steps
For a hypothetical 1,000 kW rated generator, a sequence of 400 kW, then 250 kW, then 150 kW reaches 40%, 65% and 80% of rating. The point is not those percentages; it is to reproduce the approved motor-start and essential-load sequence.
- record minimum voltage and frequency after each step;
- record recovery time to the project band;
- confirm engine, alternator and controller limits;
- verify load-shed priority and blocked starts;
- repeat the most onerous credible sequence where permitted.
Apparent power, power factor, harmonics and unbalance may govern even when kW looks acceptable.
5. Test ATS/TSE functions
IEC 60947-6-1:2026 covers transfer switching equipment within its scope and includes requirements for several transfer arrangements. The project test should identify the actual TSE class, transition type, controller, bypass/isolation arrangement and OEM procedures.
- normal-source undervoltage and phase loss;
- source-available criteria and timers;
- mechanical/electrical interlocks;
- dead-source and live-source blocking;
- manual mode and local/remote selection;
- position indication and alarm mapping;
- return-transfer and cooldown logic.
6. Prove failure modes
| Injected condition | Expected safe outcome |
|---|---|
| Failed generator start | No close to unavailable source; alarm and escalation |
| Generator ready contact stuck | Independent voltage/frequency permissive blocks unsafe close |
| Emergency breaker fails to close | Alarm, no false “bus restored” indication |
| Normal breaker fails to open | Interlock blocks unintended paralleling |
| Controller communication loss | Documented local fallback state |
| Emergency stop/lockout | Trip, alarm and controlled reset |
| Normal source returns briefly | Stability timer prevents hunting |
Use simulations or secondary injection where a live failure would create unacceptable risk. State which evidence is simulated and which is end-to-end.
7. Protect people and production
Issue a switching program, risk assessment, permit boundary and communication plan. Confirm fire systems, emergency lighting, lifts, process hazards, stored energy and restart restrictions. Assign one test director with stop authority and one person responsible for each source and process interface.
8. BOQ and bidder response
| Item | Required basis |
|---|---|
| FAT | Controller logic, I/O, alarms, simulated sequences |
| Pre-commissioning | Cables, settings, phase sequence, interlocks |
| Load test | Load bank or facility load, duration and fuel |
| Integrated SAT | Outage, transfer, steps, failures and restoration |
| Records | SOE export, PQ trend, settings, signed sheets |
| Training | Normal, manual, alarm and recovery scenarios |
9. ITP gates
- HP-01: cause-and-effect and load-step schedule approved.
- HP-02: settings, protection and interlocks verified.
- HP-03: fuel, ventilation, exhaust, cooling and starting systems accepted.
- HP-04: no-load and simulated logic tests passed.
- HP-05: load test passed with calibrated instruments.
- HP-06: integrated restoration and failure matrix witnessed and closed.
Owner handover checklist
- Do all event records use a known time base?
- Is bus restoration distinguished from process restart?
- Were load steps representative of the design case?
- Were failed start and rejected close demonstrated?
- Are settings and logic exports revision controlled?
- Are fuel autonomy and replenishment assumptions documented?
- Can operators recover from manual and alarm states?
10. Close findings by requirement, not by screenshot
Use a test register with requirement ID, scenario, initial state, command, expected result, measured result, raw-file reference, witness and disposition. A pass should identify the accepted tolerance and the design document that created it. If a timer, setting or wire changes after a failed test, record the change and repeat every affected scenario rather than replacing the earlier evidence.
Retain controller and relay event exports, power-quality trends, breaker operation counts, generator parameters, fuel level, ambient conditions and calibrated-instrument files. The signed summary should point to these records. This makes later maintenance tests comparable and prevents an unexplained commissioning value becoming the operating baseline.
Frequently asked questions
Is a monthly auto-start test enough?
No. It confirms a limited function and may not prove transfer, load response, downstream dependencies or failure handling.
Must the whole factory lose power during SAT?
Not always. Select safe staged tests and disclose their boundaries. Critical end-to-end claims need corresponding evidence.
Can the generator be sized only from connected kW?
No. Load steps, motor starting, kvar, harmonics, unbalance, derating and future duty matter. See our generator sizing guide.
What proves the ATS transfer time?
A synchronized event record showing source condition, commands, breaker states and bus voltage, not a stopwatch alone.
Prepare the integrated test
Quang Anh can help owners turn the SLD, essential-load schedule and cause-and-effect into a FAT/SAT matrix, switching program, ITP, record sheets and handover package.
Source register
- IEC 60947-6-1:2026: official IEC page.
- IEC 60364-5-56:2018: official IEC page.


Related Posts
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]
Energy-Savings Proposals: Compare Baselines Before Comparing Percent Savings
Compare factory energy-saving proposals on one auditable baseline: align boundaries, production adjustments, reporting periods, meter [...]
Fleet Operating Data Before EV Charging-Site Sizing: An Owner’s Input Pack
Build a defensible fleet-charging input pack from routes, arrival and departure times, energy, vehicle acceptance, [...]
BESS Duty-Cycle Assumptions: An Owner’s Audit for Vietnam Factories
Audit BESS duty-cycle assumptions for a Vietnam factory: services, SOC reserve, power-duration, efficiency, throughput, degradation, [...]
Rooftop Solar Investment Assumptions: A Finance-Team Challenge List for Vietnam Factories
Audit rooftop-solar investment assumptions for a Vietnam factory: load matching, yield, losses, availability, degradation, cash-flow [...]
Material Traceability for Factory Electrical Packages: Records an FDI Owner Can Audit
Define auditable material traceability for factory electrical packages: serial and batch links, receipt and quarantine, [...]
Electrical EPC Training Deliverables: An Owner’s Contract Guide
Define electrical EPC training by role, task, revision, safety boundary and acceptance evidence. Includes an [...]
Electrical Single Points of Failure: Rank the Production Consequence
Build a factory electrical consequence register around functions, shared dependencies and credible recovery paths. Compare [...]
Shared BESS for Factory Tenants: Separate Control from Energy Allocation
Define shared BESS electrical, command and tenant allocation boundaries before procurement, with a checked common-meter [...]
Electrical Handover Dossier: Make It Usable for an Overseas Facility Team
Specify an electrical handover dossier that an overseas facility team can actually use: asset links, [...]
Switchboard FAT Report Review: Evidence Before Dispatch
Review the switchboard FAT evidence chain before dispatch: assembly identity, drawing revisions, verification records, actual [...]
Factory Substation Delivery: Prove the Access Route Before Dispatch
Build a route evidence pack before dispatching factory electrical equipment: shipping envelopes, access constraints, receiving [...]