A tender statement such as “provide 20% spare electrical capacity” is not measurable until the contract identifies what is spare, where it is measured and which operating conditions apply. Twenty percent of transformer kVA, main-bus amperes, outgoing feeder ways, breaker frame size, cable-tray area or connected load are different promises. An FDI owner who accepts the phrase without a calculation boundary can receive a switchboard with empty cubicles but no usable thermal margin, or unused amperes that disappear when ambient temperature and simultaneous loading are checked.
This guide gives an owner and EPC team a practical acceptance method for a Vietnam factory. It separates five capacity dimensions, provides a reproducible worked example, and converts the result into tender schedules, BOQ lines, FAT evidence and commissioning hold points. The numbers are illustrative only. They are not a design, a protection setting, a manufacturer endorsement or approval to energize.
Technical basis checked 13 November 2026. Project-specific law, QCVN, TCVN, utility requirements and OEM data still require confirmation by the responsible parties.
1. Write one capacity definition before bidders price it
A useful requirement states the boundary, demand case, calculation method, reference conditions, minimum remaining margin and evidence. For example:
At the 400 V main switchboard bus, after all committed Phase 1 and Phase 2 loads are included at the approved simultaneous maximum demand, verified continuous assembly capacity shall be at least 120% of that demand under the scheduled installation and ambient conditions. The requirement is additional to short-circuit duty, protection, cable, transformer, room, heat-rejection and physical feeder-way checks.
This wording defines spare as a percentage of demand. Another employer may require demand not to exceed 80% of verified capacity. Those two statements are not numerically identical: 120% of demand gives a margin equal to 20% of demand, while limiting demand to 80% of capacity requires capacity equal to 125% of demand. The tender must select one convention and use it consistently.
The approved load schedule should distinguish connected load, running load, maximum demand and firm future load. Do not add an arbitrary percentage to connected kW and call the result design kVA. Record duty, diversity, operating combinations, power factor, harmonic-producing loads and contingency philosophy. Our guide to reconciling machine kW, kVA and power factor explains why vendor nameplate totals are not a demand model.
2. Separate five dimensions of spare capacity
2.1 Demand and source capacity
State the credible simultaneous demand for normal operation, planned expansion and any transfer or contingency mode. Compare it with the contractual source boundary: utility allocation, transformer firm capacity, generator duty or another defined source. An installed transformer nameplate alone does not prove upstream allocation, downstream bus capacity or N−1 performance.
2.2 Verified thermal capacity
Use the assembly and equipment ratings applicable to the real enclosure, ventilation, internal separation, installation arrangement and ambient conditions. TCVN 13724-1:2023 and TCVN 13724-2:2023 are the Vietnam standards equivalent to IEC 61439-1:2020 and IEC 61439-2:2020 for relevant low-voltage assemblies. The contract should request the design-verification basis and the manufacturer’s permissible loading for the proposed configuration. A breaker frame marking or a busbar drawing is not a substitute for assembly verification.
OEM derating data are product- and arrangement-specific. Manufacturer documentation shows that internal temperature, simultaneous device loading, connection orientation, enclosure size and ventilation can reduce usable current. Treat such documents as inputs for the offered design, not as universal factors that can be copied between brands.
2.3 Short-circuit and protection capacity
Spare continuous amperes do not create spare fault-duty margin. The design must separately verify prospective short-circuit current for the maximum source case and protection sensitivity for minimum cases. The current international calculation reference is IEC 60909-0:2026. Circuit-breaker characteristics should be specified and compared using the applicable product standard, including IEC 60947-2:2024 where relevant. The study must use the actual network, transformer, cable, motor and converter contributions; this article does not select Icu, Ics, Icw, Ipk or trip settings.
Keep the operating-case register aligned with the factory fault-data and case-register method. A future parallel transformer, closed bus tie, generator contribution or large motor can increase fault duty even when maximum demand remains unchanged.
2.4 Physical and functional expansion
Count usable outgoing functional units, not blank sheet-metal area. For each spare way, record compartment size, rated current, pole count, form of separation, interlocks, metering, control voltage, communication, cable entry direction, termination space and the manufacturer’s rules for later installation. Also reserve wall access, lifting route, safe working clearance, tray fill, penetrations and heat rejection. A spare cubicle that cannot accept the future cable bend radius or be isolated safely is not usable capacity.
2.5 Interfaces and programme capacity
Expansion also needs engineering capacity: utility approval, relay-study updates, shutdown windows, temporary supplies, test resources and document revisions. Put each boundary in the electrical interface register. Otherwise the owner may buy physical provision but still face a long outage or major redesign.
3. Worked example: why a 3,200 A label may not provide the promised margin
Assume an illustrative 400 V, three-phase main switchboard. The approved simultaneous active demand is 1.20 MW at aggregate power factor 0.90. A committed expansion adds 0.60 MW at the same power factor. Ignoring harmonics for this arithmetic demonstration, current is:
I = P / (sqrt(3) x V x PF)
- Existing demand: 1,200,000 / (1.732 x 400 x 0.90) = 1,924.5 A.
- Committed expansion: 600,000 / (1.732 x 400 x 0.90) = 962.3 A.
- Total approved demand: 2,886.8 A.
A 3,200 A nominal bus appears to leave 313.2 A, equal to 10.85% of total demand or 9.79% of the nominal rating. It therefore fails a requirement for capacity equal to 120% of demand, because that threshold is 3,464.1 A. If the contract instead requires demand to remain at or below 80% of verified capacity, the required capacity is 2,886.8 / 0.80 = 3,608.4 A.
Now assume only for screening that manufacturer evidence for the offered arrangement limits continuous capacity under the specified conditions to 90% of nominal. Verified capacity would be 2,880 A, giving a 6.8 A shortfall before harmonic, unbalance or tolerance checks. The 90% factor is not a generic design value; the project must obtain evidence for the actual assembly. The example shows why nominal current, verified capacity and contractual spare must occupy separate columns.
| Check | Illustrative result | Decision |
|---|---|---|
| Total approved demand | 2,886.8 A | Input to all comparisons |
| Nominal 3,200 A spare | 313.2 A / 10.85% of demand | Not 20% of demand |
| 120% of demand criterion | 3,464.1 A required | 3,200 A fails |
| 80% loading criterion | 3,608.4 A required | Different, more conservative definition |
| Illustrative 90% verified capacity | 2,880 A | 6.8 A below demand |
Repeat the model for normal, maintenance, emergency, bus-tie and expansion cases. A passing current calculation still does not prove voltage drop, cable ampacity, transformer loading, harmonics, neutral loading, fault duty, protection coordination or legal compliance.
4. Use a capacity schedule instead of one percentage
Create one controlled schedule with a row for every boundary: utility point, MV bus, transformer, LV main bus, bus coupler, major distribution board, generator/ATS path, UPS, BESS point of connection, rooftop PV connection and critical cable route. Recommended columns are:
- owner boundary and SLD reference;
- normal and contingency operating case;
- connected kW/kVA, approved demand and power factor;
- nominal rating and verified rating at project conditions;
- contractual spare convention and calculated margin;
- maximum and minimum fault-study results with study revision;
- spare functional units and their usable configuration;
- cable, tray, room, cooling and access provision;
- future load name, release date and responsible package;
- evidence status, deviation and closure owner.
Freeze this schedule at tender issue, design approval, manufacture release, FAT and handover. Changes to future-load assumptions must enter formal change control. This prevents the same spare from being allocated twice to production equipment, EV charging and MEP expansion.
5. Tender, BOQ, ITP and acceptance evidence
5.1 Tender data bidders need
- single-line diagrams and source operating cases;
- load schedule with firm future phases and excluded concepts;
- ambient, enclosure, ventilation, altitude and installation conditions;
- fault-level input package and protection-study responsibility;
- functional-unit schedule, cable entry and termination requirements;
- required spare convention at every named boundary;
- documents and tests required to prove the offered rating.
5.2 BOQ lines that make the promise priceable
- main switchboard assembly with stated verified current and short-time withstand requirements;
- equipped spare functional units by rating, poles and control/metering provision;
- unequipped future compartments, busbar joints and barriers approved for later extension;
- future cable containment, penetrations, earthing points and termination space;
- room ventilation or heat-rejection scope supported by equipment loss data;
- revised load flow, short-circuit, protection and arc-risk studies where contractually required;
- FAT/SAT demonstrations, record formats and as-built capacity schedule.
5.3 ITP hold points
- Design hold: approve the demand cases, spare definition and boundary schedule before equipment release.
- Manufacturer document hold: review assembly verification, device data, internal arrangement, losses and derating applicable to the offered configuration.
- FAT witness/review: confirm nameplates, bus/functional-unit arrangement, wiring, interlocks, metering and documented routine verification. Use the switchboard FAT evidence checklist rather than treating attendance as acceptance.
- Installation hold: confirm room conditions, ventilation, cable entries, torque records, earthing and access have not invalidated the approved arrangement.
- Energization hold: approve study revisions, settings, test records, SLD and safe operating procedures.
- Handover hold: issue an as-built capacity schedule with unresolved future interfaces clearly identified.
IEC and TCVN standards are contract-selected technical references unless made applicable through the relevant legal or contractual route. QCVN 25:2025/BCT is a current national electrical-safety regulation, but its precise applicability and transition must be checked for the installation and work scope. A 2026 Ministry of Construction draft for civil-building electrical systems is still a draft and is not used here as a binding factory requirement.
FAQ
Does 20% spare mean select the next larger transformer?
No. Transformer capacity is only one boundary. Verify demand, permissible loading, losses, voltage, contingency philosophy, upstream allocation, protection, LV assembly, cables, room conditions and future connection method.
Can empty feeder ways prove spare capacity?
No. Empty ways prove only some physical provision. Confirm bus and assembly capacity, compatible functional units, cable space, heat rejection, fault duty, safe isolation and the manufacturer’s extension rules.
Should spare be applied to connected load or maximum demand?
The contract must say. For investment decisions, an approved simultaneous maximum-demand model with named firm future loads is usually more meaningful than an unqualified connected-load total. Safety and equipment checks still need their own worst-case inputs.
Can a bidder use one derating factor for every switchboard?
No. Obtain product- and arrangement-specific data for the actual ambient, enclosure, connection, ventilation and simultaneous-loading conditions. Generic examples are useful for finding missing inputs, not for final selection.
What should an owner request at handover?
Request the approved and as-built capacity schedules, SLDs, load assumptions, assembly verification evidence, manufacturer data, study reports, protection settings, FAT/SAT records, deviations and future-extension instructions. Align them with the electrical handover dossier.
Owner action
Before tender award, ask every bidder to return the same capacity schedule and identify each deviation. QuangAnhcons can help an FDI owner structure the electrical design basis, tender comparison, BOQ boundaries, interface register and commissioning evidence for independent engineering review.
Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
Factory Electrical Spare Capacity: Define What 20% Means Before Tender Award
Turn a vague 20% electrical spare-capacity promise into measurable demand, thermal, fault-duty, physical-space and expansion-interface [...]
Manufacturer Certificates vs Site Test Evidence: What an FDI Owner Should Accept
Separate manufacturer certificates, factory test records and site commissioning evidence with a traceable acceptance matrix [...]
Electrical Equipment Storage Before Installation: A Release Matrix for Vietnam Factory Projects
Define storage, preservation and release controls for MV/LV switchgear, transformers, cables and auxiliaries before electrical [...]
Design Freeze Milestones for Factory Electrical Procurement: What Must Be Fixed Before Release
Freeze the right electrical design inputs before factory procurement: ratings, MV/LV interfaces, vendor documents, hold [...]
Rooftop PV Export-Limit Commissioning: Prove the Control at the Grid Meter
Commission a rooftop PV export-limit scheme at the point of connection with CT checks, load-drop [...]
BESS Auxiliary Load and Temperature Derating: A Site Acceptance Test for Net Performance
Test BESS net AC energy, standby auxiliaries, HVAC demand and temperature derating with explicit meter [...]
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]
Energy-Savings Proposals: Compare Baselines Before Comparing Percent Savings
Compare factory energy-saving proposals on one auditable baseline: align boundaries, production adjustments, reporting periods, meter [...]
Fleet Operating Data Before EV Charging-Site Sizing: An Owner’s Input Pack
Build a defensible fleet-charging input pack from routes, arrival and departure times, energy, vehicle acceptance, [...]
BESS Duty-Cycle Assumptions: An Owner’s Audit for Vietnam Factories
Audit BESS duty-cycle assumptions for a Vietnam factory: services, SOC reserve, power-duration, efficiency, throughput, degradation, [...]
Rooftop Solar Investment Assumptions: A Finance-Team Challenge List for Vietnam Factories
Audit rooftop-solar investment assumptions for a Vietnam factory: load matching, yield, losses, availability, degradation, cash-flow [...]