An infrared image with a red spot is not yet an electrical maintenance decision. A factory owner needs evidence that identifies the asset, records the operating state, explains how the temperature was measured, separates observation from diagnosis and closes the finding after repair. Without that chain, two surveys of the same switchboard cannot be compared and a dramatic colour palette can distract from the actual risk.
This guide sets out an owner-side reporting requirement for thermographic inspection of factory MV/LV equipment in Vietnam. It is a procurement and acceptance framework, not a live-work instruction, a substitute for the equipment manufacturer, or a universal temperature limit. The authorised electrical-safety procedure, access boundary, switching state and competent-person requirements must be agreed before field work starts.
1. Define the inspection question before opening the camera case
The scope should state why the survey is being commissioned. Typical questions are whether a connection is behaving differently from comparable loaded phases, whether a previously repaired point remains stable, or which assets should enter a planned outage. A vague instruction to scan the electrical system usually produces incomplete coverage and inconsistent evidence.
Build the scope from an asset register. Give every item a stable identifier tied to the single-line diagram, room and cubicle: transformer terminal box, RMU panel, MV switchgear compartment, MSB incomer, bus coupler, capacitor bank, MCC feeder, distribution board, cable termination, ATS and generator output board. Record exclusions such as inaccessible sealed compartments, equipment that cannot safely be viewed, or circuits not operating during the visit. An exclusion is an auditable fact, not an invisible gap.
Thermography should also fit the maintenance strategy. The owner can use the survey to refine a condition-based electrical maintenance plan, but one scan should not automatically replace periodic inspection, torque procedures, protection testing or OEM maintenance.
2. Establish the safe observation boundary
The method statement must identify who controls the equipment, who authorises access and what happens if an abnormal condition is observed. It should distinguish non-intrusive viewing through a suitable inspection window from any task that requires a cover or door to be opened. The survey team must not remove guards, defeat interlocks or approach exposed live parts merely to obtain a better image.
Before mobilisation, agree the asset list, expected operating state, available drawings, permitted viewpoints, electrical work permit interface, emergency stop rule and communication route to the facility duty holder. If the intended line of sight is unavailable, the report should record that limitation and recommend a safe engineering alternative rather than infer a temperature behind an opaque barrier.
3. Capture the operating context with every thermal finding
Surface temperature depends on more than equipment condition. The report should retain enough context for another reviewer to understand the measurement:
- asset ID, feeder name, phase or pole, physical location and inspection timestamp;
- equipment state, measured phase currents and, where relevant, voltage, power factor or production mode;
- ambient temperature, relative humidity when relevant, airflow, solar exposure and recent load changes;
- camera make/model, serial number, lens, detector resolution, calibration status and image file name;
- emissivity, reflected apparent temperature, object distance, atmospheric inputs and any IR-window compensation used;
- radiometric image plus matched visible-light image from a safe, repeatable viewpoint;
- measurement marker, comparison area and the reason that the reference is comparable.
ISO 18434-1:2008 covers general thermography procedures for machinery condition monitoring, including reporting and compensation for emissivity, reflected apparent temperature and attenuating media. The manufacturer’s camera documentation likewise identifies emissivity, reflected temperature, distance, atmospheric temperature, humidity and external-window compensation as measurement parameters. The report should disclose the values used; it should not silently accept camera defaults.
4. Compare like with like
A useful comparison may be the equivalent terminal on another phase carrying a similar current, an identical parallel feeder, or the same point under a comparable operating condition from an earlier survey. A neighbouring metal surface with different emissivity, geometry or airflow is not automatically a valid reference.
Consider an illustrative LV incomer observed at 32 °C ambient. Terminal surface temperatures are 68 °C, 52 °C and 50 °C, while phase currents are 286 A, 279 A and 282 A. The temperature rises above ambient are therefore 36 K, 20 K and 18 K. The hottest terminal is 18 K above the coolest matched phase. The mean current is 282.3 A and the maximum current deviation is:
Current deviation = max(|Iphase − Imean|) / Imean × 100% = 3.7 / 282.3 × 100% ≈ 1.3%.
This small descriptive current deviation makes major phase-load imbalance a weaker explanation for the 18 K matched-phase contrast. It does not prove a loose connection. Surface emissivity, reflection, contact resistance, conductor geometry, airflow, enclosure state and measurement uncertainty still need review. The result should trigger controlled investigation, not an unsupported diagnosis.
Where an engineer uses an I²R screening model to compare load cases, the assumption must be visible. For example, scaling a 36 K rise observed at 75% reference load to 90% gives 36 × (0.90/0.75)² = 51.8 K. This is only a sensitivity check that assumes constant resistance and heat transfer. It is not a forecast, an acceptance threshold or permission to keep operating.
5. Separate observation, assessment and action
Each exception should contain three distinct statements:
- Observation: what the radiometric evidence and operating data actually show.
- Assessment: plausible mechanisms, uncertainty, consequence and evidence still required.
- Action: immediate control, planned outage task, further test, responsible party and target close-out evidence.
Priority should combine repeatability, temperature contrast under comparable conditions, trend, asset criticality, protective-device coordination, fire or production consequence, accessibility and the facility’s approved risk method. A single colour or temperature band should not be presented as a universal pass/fail rule. If a contract adopts NFPA 70B:2026 or another reference, state the adopted edition and exact contractual scope; do not imply that an international document is automatically Vietnamese law.
6. Require a decision-ready exception register
A practical exception register should include asset ID, native image names, measured values, comparison basis, current/loading, preliminary priority, operating restriction if any, recommended task, outage need, responsible party, due date and closure status. Link each finding to the owner’s electrical maintenance tender scope so bidders price the same investigation and repair boundary.
For recurring events, correlate thermal findings with relay records, SCADA alarms, maintenance history and the factory outage data review. Correlation does not turn a symptom into certainty, but it helps the owner distinguish an isolated image from an operating pattern.
7. BOQ and deliverables for an RFQ
| BOQ item | Minimum measurable deliverable | Owner acceptance point |
|---|---|---|
| Planning and asset register | Tagged asset list, SLD reference, access method, expected load state and exclusions | Scope approved before mobilisation |
| Field thermography | Radiometric and visible image pair, timestamp, measurement parameters, asset ID and operating data | Traceable evidence for every inspected asset |
| Exception analysis | Observation, comparison basis, uncertainty, consequence, recommended next test and priority rationale | No unsupported failure diagnosis or generic threshold |
| Report package | PDF report, editable exception register, raw radiometric files, marked asset list and image index | Files open correctly and IDs reconcile |
| Close-out survey | Post-repair images under stated comparable load, work-order link and residual finding | Finding closed, monitored or escalated explicitly |
State whether the supplier must provide the camera’s native radiometric format. A flattened screenshot cannot support later adjustment of measurement parameters or independent review. Also define file naming and retention so that next year’s survey can retrieve the same asset and viewpoint.
8. ITP hold and witness points
Put the inspection into the project or maintenance inspection and test plan:
- H1 — method release: owner approves scope, safety interface, equipment and reporting template;
- W1 — field start: facility representative confirms equipment identity and operating state;
- W2 — critical observation: urgent finding is communicated through the agreed escalation route without unsafe intervention;
- R1 — draft review: owner checks asset coverage, image traceability, settings and evidence-to-action logic;
- H2 — close-out: repair record and repeat observation are accepted, or the residual risk is formally carried forward.
9. PV thermography is a separate scope
IEC TS 62446-3:2017 is valid and specifically defines outdoor infrared thermography for operating PV modules and plants, including equipment, ambient conditions, procedure, reporting and personnel qualification. It should not be copied wholesale into an MV/LV switchboard scope. If a factory RFQ includes both rooftop PV modules and electrical distribution equipment, split the methods, competence requirements, environmental constraints and reports.
10. FAQ for factory owners
Can the owner rank findings only by the highest measured temperature?
No. Measurement settings, comparable reference, load, trend, repeatability, asset consequence and uncertainty all matter. The report should make the priority logic auditable.
Must the equipment be at full load?
The report needs a representative, documented operating state. If representative loading is unavailable, record the limitation and avoid converting the result into a definitive pass/fail decision. Do not manipulate production or defeat safety controls solely to create a hotter image.
Does thermography replace torque checks or electrical testing?
No. It is one condition-monitoring input. The next action may require isolation, visual inspection, connection verification, resistance testing, protection review or OEM assessment under an authorised work plan.
What proves that a repair worked?
A work record plus a repeat observation at a documented, reasonably comparable operating state. The close-out should show whether the contrast disappeared, reduced, persisted or moved, and what decision follows.
Prepare a survey that can be acted on
For an RFQ or owner review of factory electrical thermography in Vietnam, provide the asset register, single-line diagram, operating constraints, maintenance history and required close-out format. Request a technical scope review to align field evidence, outage planning and corrective-action records before the survey is released.
[contact-form-7 id="7239967" title="Contact form 1"]Quick substation quotation
Loading the tool…
Multi-station and feeder project
Loading the tool…


Related Posts
Electrical Thermography Reports: What a Factory Owner Must Receive
Define a useful electrical thermography report for a Vietnam factory: asset identity, operating load, camera [...]
Backup Power Acceptance Tests: A Production-Safe Factory Plan
Plan generator and ATS acceptance around production constraints, with a controlled test sequence, P/Q load [...]
EV Charging Load Management: Requirements for a Corporate Fleet RFQ
Define site power caps, fleet priorities, offline behaviour, data, BOQ and scenario-based acceptance tests for [...]
BESS Supplier Safety Documentation: An Owner’s RFQ and Acceptance Register
A configuration-specific BESS safety-document register for RFQ, design review, FAT, SAT, change control and owner [...]
Factory Rooftop Solar Installation: Plan the Work Around Production, Not Across It
Build a rooftop PV installation plan around factory production, with roof zones, permits, lifting, isolation [...]
Factory Electrical Spare Capacity: Define What 20% Means Before Tender Award
Turn a vague 20% electrical spare-capacity promise into measurable demand, thermal, fault-duty, physical-space and expansion-interface [...]
Manufacturer Certificates vs Site Test Evidence: What an FDI Owner Should Accept
Separate manufacturer certificates, factory test records and site commissioning evidence with a traceable acceptance matrix [...]
Electrical Equipment Storage Before Installation: A Release Matrix for Vietnam Factory Projects
Define storage, preservation and release controls for MV/LV switchgear, transformers, cables and auxiliaries before electrical [...]
Design Freeze Milestones for Factory Electrical Procurement: What Must Be Fixed Before Release
Freeze the right electrical design inputs before factory procurement: ratings, MV/LV interfaces, vendor documents, hold [...]
Rooftop PV Export-Limit Commissioning: Prove the Control at the Grid Meter
Commission a rooftop PV export-limit scheme at the point of connection with CT checks, load-drop [...]
BESS Auxiliary Load and Temperature Derating: A Site Acceptance Test for Net Performance
Test BESS net AC energy, standby auxiliaries, HVAC demand and temperature derating with explicit meter [...]
Generator and ATS Restoration Test: Prove the Factory Sequence, Not Just Start-Up
Build an integrated generator and ATS acceptance test with timed source loss, load steps, failure [...]
Parallel Transformer Operation: Preconditions Before Closing the Factory Bus Tie
Review ratio, vector group, impedance, load sharing, fault level, neutral, protection and synchronism before a [...]
22 kV Cable Feeder Ampacity: Build the Route Data Pack Before Selecting Size
Turn a 22 kV factory feeder route into an auditable ampacity model covering load, soil, [...]
Factory Electrical Outage Data: From Event Logs to Continuity Decisions
Build a decision-grade factory outage data pack that separates evidence from inference, quantifies restoration stages [...]
Phased EV Depot Rollout: Power-Ready Bays vs Commissioned Chargers
Stage a fleet-charging depot by separating reserved, civil-ready, power-ready and commissioned bays, with controlled capacity, [...]
BESS Warranty Exclusions: An Industrial Buyer’s Contract Review for Vietnam
Review BESS warranty exclusions against the factory duty cycle, AC test boundary, site conditions, data [...]
Self-Funded or Third-Party Rooftop Solar? A Vietnam Factory Proposal Comparison
Compare self-funded and provider-funded rooftop solar proposals on the same energy boundary, legal structure, risk [...]
Condition-Based or Calendar-Based Electrical Maintenance? A Factory Scope Decision Guide
A buyer-side method for choosing calendar, usage and condition-based electrical maintenance using failure modes, auditable [...]
What a Factory Power-Redundancy Claim Must Prove Before an Owner Accepts It
A factory owner’s evidence checklist for power-redundancy claims: source independence, surviving load, transfer logic, protection, [...]