What is the total construction price for a 2000kVA transformer substatation in Vietnam?

Comprehensive Guide to 2000kVA Substation Construction Costs in Vietnam

1.Detailed Costs Breakdown

In the quest for economic advancement and infrastructural development, the establishment of a reliable electrical supply is paramount. The 2000KVA – 22/0.4kV substation stands as a testament to this truth, serving as a backbone for stable power delivery. Partnering with QuangAnhcons, a leader in electrical construction, ensures not just a transformer station but a promise of progress for Vietnam. In this guide, we’ll explore the intricate details of the costs, processes, and timelines involved in bringing such a pivotal project to life.

22KV Transmission Line (23.97% of Total Costs)

2000kVA substation

  • Includes high-voltage transmission line poles, iron crossarms, insulators, and other essential components.
  • 14m High-Voltage Transmission Line Pole
  • Iron Crossarm L2200x75x75x8mm/Zn
  • Crossarm Brace 60x6x920
  • 24Kv Standoff Insulator + Rod
  • 24Kv Polymer Suspension Insulator
  • AXV 50mm2 Covered Cable: Phase Wire
  • Bare AC 25mm2 Cable: Ground Wire
  • CXV 25mm2 Covered Cable: Phase Wire
  • Recloser 3P 27kV 630A 16kA/3s Include:
    • NOVA 27i
    • FDX control panel, connection acessories”
  • Power supply transformer for recloser 1P 12,7/0,23kV – 1000VA
  • DS 3P- 630A – 24kV-150 kV BIL, OD, Polymer, install on 1 pole
  • LBFCO 200A-24kV Polymer + Base
  • LA 18KV 10KA Polymer + Base
  • TU, TI
  • Medium Voltage TU, TI Support (H, V50 frame)
  • 3P 4 Wire 120/60V – 5A Electronic Meter
  • Cu/XLPE/PVC 4Cx25mm2 Cable – 0.6/1kV
  • Composite Electric Meter Box Size H500 x W300 x D200
  • Grounding for Line Section
  • Pole Foundation
  • Line Section Testing
  • Line Section Accessories: Hotline Clamp 2/0 (50-70), Insulator Cap, Grip Clip, Cable Lug, Mid/Low Voltage Tape, Bolts, LA Cover, LBFCO…
  • Labor Cost Calculated as a Package

2000KVA Substation Materials (92.59% of Total Costs)

2000kVA substation

  • Comprehensive list of materials including high-voltage poles, insulators, cable supports, substation grounding, and more.
  • 14m High-Voltage Transmission Line Pole
  • Composite Crossarm 2400x75x75x6mm + Brace: LBFCO
  • Iron Crossarm L2400x75x75x8mm/Zn + Brace
  • 24kV Standoff Polymer Insulator DR600 + Non-Lead Covered Rod
  • Low Voltage Cable Support
  • Substation Platform and Fence
  • Substation Grounding
  • Line Accessories: Insulator Cap, Cable Lug, Mid/Low Voltage Tape, Bolts, LA Cover, LBFCO, LBFCO Nameplate, Pole Nameplate, Station Nameplate, No Climbing Sign…
  • Pole Foundation
  • 24KV C/XLPE/PVC 25mm2 Covered Cable
  • CV/600V-300mm2 Cable from MBA – 6 Strands/Phase
  • CV/600V-300mm2 Cable from MBA – Neutral Wire 3 Strands/Ground
  • Cu300mm2 Cable Lug
  • 3 PHASE MBA 2000KVA- 22/0.4KV
  • LBFCO 200A-24kV Polymer + Base
  • LA 18KV 10KA
  • MSB Cabinet (ACB + reactive power compensation) Double Doort
  • ACB 3P 2500A 85KA Fixed Type
  • Reactive power compensation 1000Kvar
  • Equipment Testing
  • Labor Cost Calculated as a Package

Other Costs (7.41% of Total Costs)

2000kVA substation

  • Covering design, supervision, power cut connections, commissioning tests, and transportation costs.
  • Design and Assessment Costs
  • Supervision Costs
  • Power Cut Connection Fee
  • Commissioning Test Fee
  • Approval Documentation for Substation Installation, Completion
  • Construction Machinery & Material, Equipment Transport Cost

2000kVA substation

2.Contractor’s Lead in Construction with Investor Documentation Support

For the successful construction of the transformer station, the contractor is allocated the responsibility for managing all related operations, requiring expertise in electrical standards and coordination with power entities. The investor’s role is streamlined to providing vital legal documents, such as land rights, official licenses, and identification, all freshly notarized. The contractor’s commitment extends from the project’s inception, covering design and grid integration to the completion phase, encapsulated within a meticulously planned 60-day period, broken down into a 45-day prep and a 15-day active construction phase.

3.Financial Milestones in Transformer Station Construction Process

The financial dealings for the transformer station construction delineate into three sequential payments. It begins with an initial transaction following the contract’s finalization, enabling the contractor to dispatch materials and equipment for on-site assembly. The subsequent payment phase is activated upon the investor’s formal notification of the transformer’s arrival, allowing for its installation and the preliminary steps toward activation. The concluding financial milestone is reached with a final payment, acknowledged after the station’s energization and the comprehensive testing, a collaborative venture of the investor and contractor.

4. Operational Assurance for Clients

Clients receive a one-year warranty following construction, ensuring the project’s reliability and supporting client confidence in its operational integrity.

2000kVA substation

5. Leading in Customer Engagement and Maintaining Quality Standards

We stand committed to quality and transparency in pricing, with our rich experience in transformer station development serving as the cornerstone of our promise for customer satisfaction. Our team is available 24/7 to assist with any inquiries or support requirements. If you’re looking for personalized recommendations and an accurate quote for an 2000kVA 22/0.4kV transformer station configuration, please use the contact information we have provided. Our expert team is equipped to support you in planning, cost evaluation, and legal obligations to ensure a smooth and efficient construction process.

6.Engage with Us for a Customized Project Approach

Opting for QuangAnhcons for the construction of your 2000kVA – 22/0.4KV substation is not merely a project choice; it’s a commitment to elevating energy efficiency, reinforcing system stability, and contributing to socio-economic progress. Through our commitment to transparency in pricing, excellence in service, and technical mastery, we ensure that your partnership with us will lead the way to exemplary achievements in the realm of electricity.

2000kVA substation

Quang Anh CE Co.,LTD

Contact Number: (+84) 9 1975 8191

Email Address: project@quanganhcons.com

Office Location:Unit 02, 08th floor, Pearl Plaza Building, 561A Dien Bien Phu Street, Ward 25, Binh Thanh District, Ho Chi Minh City

Operational Hours: Monday to Friday, from 8:00 am to 5:00 pm.

 

Please Note: All provided figures are estimations and may vary based on site conditions and market variables. Our direct communication channels are open for real-time updates and custom solutions.

 