750kVA Substation – How much is the construction cost in Vietnam?

Constructing a transformer station is a complex and significant undertaking that requires careful planning, precision, and expertise. QuangAnhcons is at the forefront of this innovative venture, offering comprehensive solutions for the installation of a 750kVA – 22/0.4KV substation. This document serves as a detailed guide, outlining the essential aspects of construction, including an estimate of costs, the main work content, payment structure, warranty, customer support, and contact information for tailored experiences. Our goal is to ensure transparency, efficiency, and reliability throughout the construction process, making it seamless for investors and stakeholders involved.

Embarking on this journey, we delve into the intricate details of what makes a transformer station construction project successful. From the initial steps of legal documentation and preparation to the final touches of commissioning and energization, each phase is meticulously planned and executed. Our commitment to excellence is reflected in our detailed construction estimate table, which presents a clear breakdown of costs associated with the project, including materials, labor, and other essential expenses.

Understanding the gravity of this investment, we aim to provide our clients with a solid foundation of knowledge, enabling informed decision-making. Whether it’s navigating through the complexities of construction or ensuring compliance with electrical equipment standards, QuangAnhcons stands ready to guide you through each step, promising a result that not only meets but exceeds expectations. Join us as we explore the depths of transformer station construction, offering a glimpse into the dedication and precision that go into powering communities and propelling Vietnam into a future of electrical excellence.

750kva substation

1.Construction Estimate Table Overview

The provision of a 750kVA – 22/0.4KV substation is an intricate venture demanding meticulous planning and execution. Below is a breakdown of the various stages and associated costs:

– 22kV Transmission Line:

750kva substation

– This includes 14m High-Voltage Transmission Line Poles, Iron Crossarms, Insulators, and the requisite cabling and grounding equipment.

  • 14m High-Voltage Transmission Line Pole
  • Iron Crossarm L2200x75x75x8mm/Zn
  • Crossarm Brace 60x6x920
  • 24Kv Standoff Insulator + Rod
  • 24Kv Polymer Suspension Insulator
  • AXV 50mm2 Covered Cable: Phase Wire
  • Bare AC 25mm2 Cable: Ground Wire
  • CXV 25mm2 Covered Cable: Phase Wire
  • LBFCO 200A-24kV Polymer + Base
  • LA 18KV 10KA Polymer + Base
  • TU, TI
  • Medium Voltage TU, TI Support (H, V50 frame)
  • 3P 4 Wire 120/60V – 5A Electronic Meter
  • Cu/XLPE/PVC 4Cx25mm2 Cable – 0.6/1kV
  • Composite Electric Meter Box Size H500 x W300 x D200
  • Grounding for Line Section
  • Pole Foundation
  • Line Section Testing
  • Line Section Accessories: Hotline Clamp 2/0 (50-70), Insulator Cap, Grip Clip, Cable Lug, Mid/Low Voltage Tape, Bolts, LA Cover, LBFCO…
  • Labor Cost Calculated as a Package

– Substation 750kVA – 22/0.4KV Materials: 

750kva substation

– Key materials encompass High-Voltage Poles, Crossarms, Insulators, Substation Grounding, and a comprehensive list of accessories and equipment necessary for robust substation functionality.

  • 14m High-Voltage Transmission Line Pole
  • Composite Crossarm 2400x75x75x6mm + Brace: LBFCO
  • Iron Crossarm L2400x75x75x8mm/Zn + Brace
  • 24kV Standoff Polymer Insulator DR600 + Non-Lead Covered Rod
  • Low Voltage Cable Support
  • Substation Platform and Fence
  • Substation Grounding
  • Line Accessories: Insulator Cap, Cable Lug, Mid/Low Voltage Tape, Bolts, LA Cover, LBFCO, LBFCO Nameplate, Pole Nameplate, Station Nameplate, No Climbing Sign…
  • Pole Foundation
  • 24KV C/XLPE/PVC 25mm2 Covered Cable
  • CV/600V-185mm2 Cable from MBA – 4 Strands/Phase
  • CV/600V-185mm2 Cable from MBA – Neutral Wire 2 Strands/Ground
  • Cu185mm2 Cable Lug
  • 3 PHASE 750KVA transformer – 22/0.4KV
  • LBFCO 200A-24kV Polymer + Base
  • LA 18KV 10KA
  • MSB Cabinet (MCCB + reactive power compensation), Double Door, Including 100mm Base Height, 50mm Canopy Height
  • MCCB 3P 1250A 85KA Fixed Type
  • Reactive power compensation 375Kvar
  • Equipment Testing
  • Labor Cost Calculated as a Package

– Other Costs:

– Encompassing design, supervision, connection fees, and the logistical aspects of machinery and material transport.

In total cost, you can find all of the items mentioned above in our video.

2.Main Work Content

– The contractor will be responsible for all related procedures, while the investor will only provide the legal documents: land use right certificate (or land lease agreement), business license, identification card (or passport) of the legal representative, and environmental protection commitment (if any), with each document type having 04 notarized sets not older than 03 months. The contractor is responsible for constructing the project according to current electrical equipment standards, coordinating with the relevant electrical units to complete the electricity supply procedures until the project is energized, which includes: design documents, agreement on connecting to the power grid, coordinating supervision with the power utility, organizing acceptance checks, and other related tasks.

The construction process is thorough, starting from the sanction of documentation to the full assembly of the transformer station, in line with stringent electrical equipment standards. Collaboration with relevant electrical units is key to seamless electricity supply procedures. Typically, the preparatory phase spans 45 days, with the construction period lasting an additional 15 days, culminating in a total of 60 days to project completion.

3.Payment Structure

Payments for the transformer station construction project are structured into three stages:

The first payment is made immediately after the contract is signed, following which the contractor proceeds to transport materials and equipment to the site for installation.

The second payment occurs once the investor has been notified of the transformer’s delivery to the site; after this payment, the contractor will deliver the transformer to the site and complete the installation in preparation for commissioning and energization of the transformer station.

The final payment is made after the energization and testing have been completed by both the investor and the contractor.

750kva substation

4.Warranty and Customer Support:

A 12-month warranty period ensures operational integrity and client reassurance post-construction.

5.Customer Engagement and Service Excellence:

Our commitment to quality and transparent pricing, coupled with our experience in transformer station development, ensures customer satisfaction. We offer 24/7 support for any inquiries or assistance needed.

For tailored guidance and a precise quotation that meets your specific needs for a complete 750kVA 22/0.4kV transformer station setup, please connect with us using the contact details we’ve provided. Our team of experts is ready to facilitate the planning, cost assessment, and legal procedures to guarantee a smooth construction trajectory.

6.Contact for a Tailored Experience

The investment in a 750kVA – 22/0.4KV substation by QuangAnhcons represents more than just a construction project; it’s a commitment to energy efficiency, system reliability, and socioeconomic advancement. With transparent pricing, impeccable service, and technical prowess, we assure you that your partnership with us will illuminate pathways to electrical excellence.

750kva substation

Quang Anh CE Co.,LTD

– Contact Number: (+84) 9 1975 8191

– Email Address: project@quanganhcons.com

– Office Location:Unit 02, 08th floor, Pearl Plaza Building, 561A Dien Bien Phu Street, Ward 25, Binh Thanh District, Ho Chi Minh City

– Operational Hours: Monday to Friday, from 8:00 am to 5:00 pm.

 

Please Note: All provided figures are estimations and may vary based on site conditions and market variables. Our direct communication channels are open for real-time updates and custom solutions.

 